#PMP Question #4638
A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that he is facing a critical problem that will prevent him from completing his assigned task.
What should the project manager do?
Answers:
a. Ask the team member to follow the approved communications management plan to communicate his issue.
b. Schedule a meeting with the concerned team member to review and update the issue log together.
c. Review the risk register with the team member to find the proper response action for this issue.
d. Ask the team member to raise a change request to assess the issue in detail.
Answers #4638
Anonymous Quiz
17%
a
36%
b
36%
c
11%
d
👍2
#CAPM Question #3498
Which of the following are not inputs for the validate scope process?
Answers:
a. The project management plan which containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
b. The validated deliverables, completed and checked for correctness by the perform quality control process.
c. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.
d. The RACI matrix, describing accountabilities for scope validation and acceptance.
Answers #3498
Anonymous Quiz
12%
a
24%
b
24%
c
41%
d
🤔2
#PfMP Question #2651
The members of your Portfolio Review Board and other key stakeholders tend to be risk adverse as the company has survived recent recessions and is profitable. However, in an upcoming meeting with the corporate Board of Directors, they have asked you to show the frequency of meeting certain cost objectives at various percent points. For example assume the portfolio is to meet a $41,000 target in the next month, to be 75% confident this will occur, a forecast of $50,000 is needed. This means you need to show:
#PMP Question #4646
A project manager presented the project schedule to the main stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?
Answers:
a. Hold a stakeholder meeting to align timelines and scope expectations.
b. Crash the schedule to shorten the timeline while keeping the scope unchanged.
c. Update the cost management plan to allocate more resources to the project to finish the scope earlier.
d. Reduce the scope of the project by removing activities and shortening the timeline.
Answers #4646
Anonymous Quiz
54%
a
19%
b
16%
c
11%
d
👍1
#PfMP Question #1995
Glenn is currently involved in the Authorize Portfolio process. He is describing to you a tool and technique he is currently applying which identifies which portfolio components have been assigned resources. What is Glenn describing?