#CAPM Question #3586
The project manager is looking at the project resource needs from past projects. Based on this information, the project manager is concerned about the ability to acquire enough resources for the project in three months' time. Which of the following is least likely to help the project manager?
Answers:
a. Ensure that the functional manager understand the project resource histogram.
b. Show the sponsor the information and explain the project's concerns.
c. Determine metric that can be used as early warning signs to indicate when resources will not be available.
d. Ask functional managers for their opinions.
The project manager is looking at the project resource needs from past projects. Based on this information, the project manager is concerned about the ability to acquire enough resources for the project in three months' time. Which of the following is least likely to help the project manager?
Answers:
a. Ensure that the functional manager understand the project resource histogram.
b. Show the sponsor the information and explain the project's concerns.
c. Determine metric that can be used as early warning signs to indicate when resources will not be available.
d. Ask functional managers for their opinions.
What resources and chapters from the PMBOK Guide and the Process Groups: A Practice Guide should be reviewed to learn about planning and managing the quality of products or deliverables for the PMP Certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-7-plan-and-manage-quality-of-products-deliverables/
#QualityManagement #PMP #Certification #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-7-plan-and-manage-quality-of-products-deliverables/
#QualityManagement #PMP #Certification #ProjectManagement
KnowledgeMap
PMP Plan and Manage Quality
Learn how to PMP plan and manage quality of project deliverables with key tasks and resources for your certification.
👍2
#PMP Question #3272
The project manager has learned that the project sponsor is unhappy with the development of the project requirements.
In order to realign the project with the sponsor's expectations, what should the project manager do?
The project manager has learned that the project sponsor is unhappy with the development of the project requirements.
In order to realign the project with the sponsor's expectations, what should the project manager do?
❤1
What does the Construction Project Communications Course for the PMI-CP™ Certification cover, and how can participants complete it?
Referer to:https://knowledgemap.pm/certifications/pmi-cp/complete-course-modules/construction-project-communications-course/
#PMICP #ConstructionCommunication #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pmi-cp/complete-course-modules/construction-project-communications-course/
#PMICP #ConstructionCommunication #ProjectManagement
KnowledgeMap
PMI-CP Construction Project Communications Course
Master effective communication in construction projects with the Construction Project Communications Course PMI-CP certification.
👍1
#PMP Question #4733
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do first?
Answers:
a. Escalate this issue to senior management, as the supplier is not following the procurement contract.
b. Request a revision of the procurement contract to include specifications for the parts.
c. Request a cancellation of the procurement contract with the supplier and impose a penalty.
d. Review the procurement contract and ask the supplier to negotiate a solution.
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do first?
Answers:
a. Escalate this issue to senior management, as the supplier is not following the procurement contract.
b. Request a revision of the procurement contract to include specifications for the parts.
c. Request a cancellation of the procurement contract with the supplier and impose a penalty.
d. Review the procurement contract and ask the supplier to negotiate a solution.
❤1👍1
What are the benefits of becoming a PMI member for PMP certification candidates?
Referer to:https://knowledgemap.pm/certifications/pmp/certification-process/pmi-membership-benefits-for-pmp/
#PMI #PMP #Benefits #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pmp/certification-process/pmi-membership-benefits-for-pmp/
#PMI #PMP #Benefits #ProjectManagement
KnowledgeMap
PMP PMI Membership Benefits
Explore PMI Membership Benefits for PMP—save on exams, access the PMBOK Guide, and gain exclusive resources to advance your career.
👍2
#PMP Question #766
In which project management process group is the detailed project budget created?
In which project management process group is the detailed project budget created?
Anonymous Quiz
10%
a. Initiating
6%
b. Before the project management process
79%
c. Planning
6%
d. Executing
👍1
What should you do after passing the PMI-RMP exam to consolidate your knowledge and complete the certification process?
Referer to:https://knowledgemap.pm/certifications/rmp/domains/domains-learned/
#PMIRMP #RiskManagement #Learning
Referer to:https://knowledgemap.pm/certifications/rmp/domains/domains-learned/
#PMIRMP #RiskManagement #Learning
KnowledgeMap
PMI-RMP Domains Learned
After passing the exam, learn how to strengthen your skills and progress with PMI-RMP Domains Learned for certification success.
👍1
#PMP Question #1653
A project is 70% complete when the project sponsor requests an additional deliverable.
What should the project manager do first?
A project is 70% complete when the project sponsor requests an additional deliverable.
What should the project manager do first?
Anonymous Quiz
0%
a. Reject the request as being too late and leading to major scope creep.
30%
b. Submit the request to the change control board (CCB) for a decision.
2%
c. Negotiate with the project sponsor on the possible alternatives.
67%
d. Determine the possible impact of this change on all aspects of the project.
How will you be notified to submit payment for the PMI-RMP certification, and what is the recommended way for you to complete the payment?
Referer to:https://knowledgemap.pm/certifications/rmp/certification-process/submit-payment/
#PMIRMP #Certification #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/rmp/certification-process/submit-payment/
#PMIRMP #Certification #ProjectManagement
KnowledgeMap
PMI-RMP Payment Process
Easily complete the PMI-RMP Certification Payment Process online through My PMI after approval. Fast and convenient payment steps explained.
👍2
#PMP Question #4939
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to collaborate.
What should the project manager do to keep the team performing as effectively as possible?
Answers:
a. Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance.
b. Transition the team from an agile approach to a predictive approach for better performance control.
c. Provide the team with virtual collaboration software and training on the software to minimize disruption.
d. Evaluate project performance and step in if performance decreases to an unacceptable level.
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to collaborate.
What should the project manager do to keep the team performing as effectively as possible?
Answers:
a. Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance.
b. Transition the team from an agile approach to a predictive approach for better performance control.
c. Provide the team with virtual collaboration software and training on the software to minimize disruption.
d. Evaluate project performance and step in if performance decreases to an unacceptable level.
👍1
What steps are involved in authorizing a program and developing the program management plan during the Program Definition phase of the PgMP certification?
Referer to:https://knowledgemap.pm/certifications/pgmp/learning-the-program-life-cycle/learn-program-definition/
#PgMP #Certification #ProgramDefinitionPhase #ProgramManagement
Referer to:https://knowledgemap.pm/certifications/pgmp/learning-the-program-life-cycle/learn-program-definition/
#PgMP #Certification #ProgramDefinitionPhase #ProgramManagement
KnowledgeMap
PgMP Program Definition Phase
Master the PgMP Program Definition Phase Activities with key tasks, tools, and resources to align programs with strategic objectives.
❤1👍1
#CAPM Question #1349
A resource management plan includes all of the following except:
A resource management plan includes all of the following except:
Anonymous Quiz
23%
a. Guidance on how to acquire team and physical resources for the project.
13%
b. Roles and responsibilities.
15%
c. Guidance on how project team resources should be released.
49%
d. Project team directory.
🤔1
How do you schedule your PMI-CP™ certification exam once you become eligible?
Referer to:https://knowledgemap.pm/certifications/pmi-cp/pmi-cp-certification-process/schedule-exam-appointment/
#PMICP #ProjectManagement #PMI
Referer to:https://knowledgemap.pm/certifications/pmi-cp/pmi-cp-certification-process/schedule-exam-appointment/
#PMICP #ProjectManagement #PMI
KnowledgeMap
PMI-CP Exam Scheduling
Learn about PMI-CP certification exam scheduling, including how to use your eligibility code to book your test online or by phone.
👍2
#PMP Question #1794
What does an iteration burndown chart track?
What does an iteration burndown chart track?
Anonymous Quiz
20%
a. Work remaining to be completed for the product.
68%
b. Work remaining to be completed in the iteration backlog.
12%
c. Work finished so far in the iteration.
0%
d. Work ideally completed on average in every iteration.
Why is embracing change a fundamental principle in agile, and how do PMI-ACP candidates learn to apply it in dynamic project environments?
Referer to:https://knowledgemap.pm/certifications/acp/domain-1-mindset/acp-embrace-change/
#Agile #EmbraceChange #PMIACP
Referer to:https://knowledgemap.pm/certifications/acp/domain-1-mindset/acp-embrace-change/
#Agile #EmbraceChange #PMIACP
KnowledgeMap
PMI-ACP Embrace Change
Learn how the PMI-ACP Embrace Change in Agile approach helps teams stay flexible, adaptive, and responsive in dynamic project environments.
👍1