𝗞𝗻𝗼𝘄𝗹𝗲𝗱𝗴𝗲𝗠𝗮𝗽
2K subscribers
84 photos
304 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#PMP Question #3873
An organization is introducing agile to its projects. During an informal discussion, the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team.
What should the project manager do?
Answers:
a. The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs.
b. The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team.
c. The project manager should allow the resources to periodically choose on which team they would like to work.
d. The project manager should indicate that the team members have already been assigned to a team through workforce optimization.
🤔1
Answers #3873
Anonymous Quiz
30%
a
4%
b
48%
c
19%
d
👍2
#CAPM Question #745
The project life cycle differs from the product life cycle in that the project life cycle:
Anonymous Quiz
3%
a. Does not incorporate a methodology
45%
b. Is temporary in nature
18%
c. Can spawn many projects
33%
d. Describes project management activities
👍1
#PMI-PBA Question #125
The project team is working on test scripts to test a solution.
Which source can be used for building tests of end-to-end business processes across business functions and systems?
Anonymous Quiz
19%
a. Feature model
19%
b. Use case
33%
c. Prototype model
30%
d. Context diagram
🤔1
#PMP Question #5305
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months.
Based on the new timeline, what should the project manager do?
Answers:
a. Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders.
b. Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline.
c. Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule.
d. Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline.
Answers #5305
Anonymous Quiz
9%
a
87%
b
0%
c
4%
d
👍1
#PMP Question #1679
Which statement on constructive changes is false?
Answers:
a. Constructive changes are contract changes which are construed from actions taken by either party, not from a change document.
b. Changes in projects under contract are called constructive changes if they yield benefits for both parties.
c. Constructive changes are a frequent cause of disputes and claims between one contract party and another.
d. Field changes should be meticulously documented to avoid an interpretation as constructive change.
Answers #1679
Anonymous Quiz
16%
a
47%
b
16%
c
21%
d
🤔1
#PMP Question #5021
A new systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution document.
What should the project manager do to avoid a delay in the project?
Answers:
a. Ask the accounting manager to delegate a team member who can support the project.
b. Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed.
c. Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource.
d. Begin discussions with other functional managers and meet with the accounting manager later.
👍1