𝗞𝗻𝗼𝘄𝗹𝗲𝗱𝗴𝗲𝗠𝗮𝗽
2K subscribers
85 photos
315 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#CAPM Question #3586
The project manager is looking at the project resource needs from past projects. Based on this information, the project manager is concerned about the ability to acquire enough resources for the project in three months' time. Which of the following is least likely to help the project manager?
Answers:
a. Ensure that the functional manager understand the project resource histogram.
b. Show the sponsor the information and explain the project's concerns.
c. Determine metric that can be used as early warning signs to indicate when resources will not be available.
d. Ask functional managers for their opinions.
Answers #3586
Anonymous Quiz
22%
a
11%
b
30%
c
37%
d
🤔1
#PMP Question #3272
The project manager has learned that the project sponsor is unhappy with the development of the project requirements.
In order to realign the project with the sponsor's expectations, what should the project manager do?
1
#PMP Question #4733
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do first?
Answers:
a. Escalate this issue to senior management, as the supplier is not following the procurement contract.
b. Request a revision of the procurement contract to include specifications for the parts.
c. Request a cancellation of the procurement contract with the supplier and impose a penalty.
d. Review the procurement contract and ask the supplier to negotiate a solution.
1👍1
#PMP Question #766
In which project management process group is the detailed project budget created?
Anonymous Quiz
10%
a. Initiating
6%
b. Before the project management process
79%
c. Planning
6%
d. Executing
👍1
#PMP Question #4939
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to collaborate.
What should the project manager do to keep the team performing as effectively as possible?
Answers:
a. Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance.
b. Transition the team from an agile approach to a predictive approach for better performance control.
c. Provide the team with virtual collaboration software and training on the software to minimize disruption.
d. Evaluate project performance and step in if performance decreases to an unacceptable level.
👍1
Answers #4939
Anonymous Quiz
3%
a
7%
b
59%
c
31%
d
👍1