#CAPM Question #982
A management point in a work breakdown structure (WBS) used to consolidate and process work package data and forward the results to the project manager is called:
Anonymous Quiz
52%
a. Control account
21%
b. Chart of accounts
21%
c. Control limit
6%
d. Account limit
#PMP Question #2665
A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
🔔Join Our June Group of 🔤🔤🔤🔤 Prep!
Training Starts Soon – You Still Have Time to Enroll!

Your organization may be doing things right, but is it doing the right things? As a PfMP, your role is to ensure it is. The PfMP proves your ability to manage portfolios aligned with strategic goals. Mature organizations complete 35% more programs with lower costs and risks according to PMI thought leadership report, Delivering on Strategy: The Power of Project Portfolio Management.

â„šī¸About the Preparation Course:
➖ Price: â‚Ŧ1000â­ī¸
➖ Duration: 4 months
➖ Full access to the KnowledgeMap platform included.

⏰We will be holding an open onboarding on June, 2 at 16:00GMT.
🔗Join us: https://calendar.app.google/iYbCNCFKuVdTsZZT7

PfMP — your gateway to strategic leadership.


❓Got Questions?
Ask
@AnatoliiSavin! Founder & Chief Mentor of KnowledgeMap is here to guide your certification journey. Reach out for expert advice and personalized mentoring!

â­ī¸ Ways to Save 💰:
â­ī¸ Military Support: Education is free for Ukrainian veterans and military personnel.
â­ī¸ Flexible Payment Options: Pay in 2-3 installments for easier budgeting.
â­ī¸ Early Birds: Pay in full by June, 2 for a 20% discount.
â­ī¸Self-Study: Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
â­ī¸ For PMI Ukraine members: additional 10% discount.


📌 Note: đŸ“Ŗ
🔸The next PMI-CP Prep group begins on June 16, 2025.
🔸The next PMP Prep group begins on July 1, 2025.
All certifications of Marathon '25
- KnowledgeMap.pm/Marathon

đŸ“ĸ Join our PfMP chat here. â¤ī¸đŸ“ą

Please also join the certifications preparation channels:
📱Telegram: t.me/KnowledgeMap
📱WhatsApp: chat.whatsapp.com/D9rnSipBWiZLPsqvW1wJl3
📱LinkedIn: linkedin.com/company/knowledge-map

#pfmp #pfmpcertification #pfmpexam #pfmpprep #projectportfoliomanagement #knowledgemap
Please open Telegram to view this post
VIEW IN TELEGRAM
đŸ”Ĩ1
#PMP Question #988
You are meeting with the client for product verification and sign-off. During the walk-through, the client asks you to add a small feature that was not in the original plan. This will take you 3 weeks to do but will require regression testing that will take an additional 6 weeks.
How should you respond?
Answers:
a. Suggest that the client create a new project to accommodate any changes and additions to the original project.
b. Refer to WBS and point out that the new test was not part of the project scope and can therefore not be included.
c. Use management reserve from the budget to get the test done as quickly as possible.
d. Work overtime and try and get the addition in and tested in 6 weeks.
❤1
#PMP Question #770
The person who should be in control of the project during project planning is the:
Anonymous Quiz
80%
a. Project manager.
2%
b. Team member.
7%
c. Functional manager.
11%
d. Sponsor.
❤1👍1
#CAPM Question #1438
Which knowledge area does NOT provide input to cost budgeting?
Anonymous Quiz
32%
a. Schedule.
29%
b. Quality.
8%
c. Scope.
31%
d. Risk.
đŸĨ´2
#PMP Question #2975
A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.
What should the project manager do to resolve the team member's concerns?
Answers:
a. Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.
b. Use a problem-solving approach and set up a discussion with the team lead and team member.
c. Establish guidelines for team leads to ensure that all team members are appropriately treated.
d. Provide direction to the team lead on how to resolve the issue with the team member directly.