#PMP Question #4925
During an agile project, a project manager lost one of the resources and, at the same time, uncovered new requirements, which were added to the backlog.
What should the project manager do next?
Answers:
a. Reevaluate the project schedule as the velocity will be impacted by the loss of resources.
b. Reevaluate the backlog priority with the product owner since the velocity has been impacted.
c. Reevaluate the scope of the current iteration to keep the same velocity and timeline.
d. Reevaluate the velocity as the iteration duration will be impacted by new requirements.
#PMP Question #2934
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress (WIP) and points this out to the project manager.
What should the project manager do?
Answers:
a. Schedule a one-on-one meeting with the functional manager to prove the project is on schedule.
b. Listen carefully and show understanding of the growing needs of the functional manager.
c. Admit that the functional manager is right and promise to rectify the situation immediately.
d. Show the functional manager that the progress of the project is based on the schedule.
#PMP Question #2897
The Scrum team working with the quality department has been drifting away from the business unit due to unclear product requirements. Now, in the third sprint, both teams have been at a standstill for several days.
What should the project leader do to resolve this situation?
#PfMP Question #2177
A portfolio manager is looking for a starting point to develop the Portfolio.
Which of the following is right?
Anonymous Quiz
45%
a. Portfolio Charter
21%
b. Inventory of work
5%
c. Portfolio Communication Plan
29%
d. Portfolio Roadmap
๐Ÿ‘2
#CAPM Question #1803
Who is responsible for making sure that each user story is associated with at least one user role or persona?
Anonymous Quiz
8%
a. User
66%
b. Developer
15%
c. Customer
10%
d. Persona
๐Ÿค”6
#PMP Question #5131
A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously. However, the tasks do not have the same result as the impediment.
What should the project manager do?
๐Ÿ””Join Our June Group of
๐Ÿคฉ๐Ÿคฉ๐Ÿคฉโž–๐Ÿคฉ๐Ÿคฉ๐Ÿคฉ๐Ÿคฉ๐Ÿคฉ Prep!
Training Starts Soon โ€“ You Still Have Time to Enroll!

PMI-PMO Certified Practitioner (PMI-PMOCP) certification validates your expertise in leading and optimizing PMOs to deliver strategic value tailored to an organizationโ€™s unique needs.

โ„น๏ธ About the Preparation Course:
โž– Price: โ‚ฌ655โญ๏ธ
โž– Duration: 3 months
โž– Certificate: 10 contact hours of PMO-focused education (meets PMI requirements)
โž– Full access to the KnowledgeMap platform included.

โฐWe will be holding an open onboarding on June, 16 at 16:00GMT.
๐Ÿ”—Join us: https://calendar.app.google/iAGuKvGqmDrq2KjW7

Be a strategist, not just a manager. PMI-PMOCP.


๐ŸคฉGot Questions?
Ask
@AnatoliiSavin! Founder & Chief Mentor of KnowledgeMap is here to guide your certification journey. Reach out for expert advice and personalized mentoring!

โญ๏ธ Ways to Save ๐Ÿ’ฐ:
โญ๏ธMilitary Support: Education is free for Ukrainian veterans and military personnel.
โญ๏ธFlexible Payment Options: Pay in 2-3 installments for easier budgeting.
โญ๏ธEarly Birds: Pay in full by June, 16 for a 20% discount.
โญ๏ธSelf-Study: Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
โญ๏ธFor PMI Ukraine members: additional 10% discount.

๐Ÿ“Œ Note: ๐Ÿ“ฃ
๐Ÿ”ธThe next PMP Prep group begins on July 1, 2025.
๐Ÿ”ธThe next PMI-CP Prep group begins on July 14, 2025.
๐Ÿ”ธ The next PSM I Prep group starts on July 28, 2025.
All certifications of Marathon '25
- KnowledgeMap.pm/Marathon

๐Ÿ“ข ๐ŸคฉJoin our PMI-PMOCP chat here. โค๏ธ๐Ÿ“ฑ

Please also join the certifications preparation channels:
๐Ÿ“ฑTelegram: t.me/KnowledgeMap
๐Ÿ“ฑWhatsApp: chat.whatsapp.com/D9rnSipBWiZLPsqvW1wJl3
๐Ÿ“ฑLinkedIn: linkedin.com/company/knowledge-map

#PMI #PMO #certification #KnowledgeMap
Please open Telegram to view this post
VIEW IN TELEGRAM
#PMP Question #3319
A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the beginning of the project have changed.
What should the project manager do?