#CAPM Question #854
Which of the following is true about total float?
Answers:
a. It is the amount of time an activity can slip before impacting the immediate successor task.
b. It is the amount of time an activity can slip before impacting the end date of the project.
c. It is a constant value throughout project execution.
d. It is assigned to activities during activity duration estimating.
#CAPM Question #4572
In an adaptive project management environment, the project manager is evaluating the success of a recently completed project task. Which of the following would be the most appropriate criterion for interpreting the success of this task?
#PMP Question #5196
A project manager is working on a project with multiple workstreams. One of the workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen again?
#PMP Question #5343
A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and sustained?
๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
๐Ÿ†•๐Ÿ””Join Our April Group of ๐Ÿ” ๐Ÿ” ๐Ÿ” -๐Ÿ” ๐Ÿ” ๐Ÿ”  Prep! Training Starts Soon โ€“ You Still Have Time to Enroll! If you analyze requirements or drive business change, the PMI-PBA certification is for you. โ„น๏ธAbout the Preparation Course: โž– Price: โ‚ฌ555โญ๏ธ โž– Duration: 3 monthsโ€ฆ
Still deciding whether to join the PMI-PBA Prep Group? Here's a great reason to say yes!

Your mentor for this training will be Denis Gobov ( @Dgobov ):
- Business analyst and trainer with more than 20  years of experience.
- Head of Business Analysis Capability at DataArt
- Editor at artofba.com/blog
- The co-author of the certification exam for CBAP based on BABOK 3.0.
- The first Ukrainian analyst who passed certification exams from leading organizations in business analysis and requirement engineering areas: CBAP (IIBA), PMI-PBA (PMI), CPRE (IREB).
- PhD
- Winner of the award "Best professional in the field of business analysis in 2013 and 2016โ€, IT Ukraine Association and "The Best Business Analyst in 2017", ITNetwork

โœ… Register for the free onboarding session: calendar.app.google/KvpVeiefSr1MNjAJA
๐Ÿ’ฌ Join the group chat on Telegram: t.me/+4kd3mhEDQS5lOTI6

Letโ€™s get you PBA-ready! ๐Ÿ’ผ๐Ÿ“š
๐Ÿ”ฅ2
#PMI-RMP Question #1546
One of the risks identi๏ฌed during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?