๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
1.97K subscribers
78 photos
208 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
๐Ÿ“ข New from KnowledgeMap: PMP Preparation Through Simulation

Weโ€™re pleased to announce the launch of a new voice-based simulation game developed as part of our PMP Preparation Through Simulation series designed to strengthen your readiness for the PMPยฎ exam.
This scenario focuses on Emotional Intelligence, a core competency for project managers that often determines the success or failure of high-stakes interactions. The game places you in realistic project situations where your ability to navigate difficult conversations with clients and stakeholders is put to the test.

๐ŸŽฎ Access the simulation:
https://chatgpt.com/g/g-67ea47245438819192edc973d59e9285-pmp-game-2-emotional-intelligence-simulator

โ–ถ๏ธ Walkthrough:
https://youtu.be/ypN8nrKShe4

๐Ÿ’ฌ Share your feedback:
https://www.linkedin.com/feed/update/urn:li:activity:7312449638316339200/

This is more than a practice tool, itโ€™s an opportunity to practice application of project management theory in complex, human-centered contexts. Your feedback will directly shape future simulations in this evolving series.
๐Ÿ”ฅ5
#CAPM Question #854
Which of the following is true about total float?
Answers:
a. It is the amount of time an activity can slip before impacting the immediate successor task.
b. It is the amount of time an activity can slip before impacting the end date of the project.
c. It is a constant value throughout project execution.
d. It is assigned to activities during activity duration estimating.
#CAPM Question #4572
In an adaptive project management environment, the project manager is evaluating the success of a recently completed project task. Which of the following would be the most appropriate criterion for interpreting the success of this task?
#PMP Question #5196
A project manager is working on a project with multiple workstreams. One of the workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen again?
#PMP Question #5343
A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and sustained?