Daily Question #1999
The portfolio management process ensures the components are aligned to goals. However, it is driven by:
The portfolio management process ensures the components are aligned to goals. However, it is driven by:
Anonymous Quiz
2%
a. Viability
16%
b. Value and benefits
70%
c. Organizational strategy and objectives
11%
d. Interdependencies and resource constraints
๐1
Daily Question #1051
Conformance to specification and fitness for use are two tenants of quality management.
Meeting these objectives impacts:
Conformance to specification and fitness for use are two tenants of quality management.
Meeting these objectives impacts:
Anonymous Quiz
47%
a. Customer satisfaction.
17%
b. Scope validation.
33%
c. Quality control.
2%
d. Management responsibility.
๐2
Daily Question #2710
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended bene๏ฌts of the project align with the strategic objectives of the business.
What should the project manager do ๏ฌrst?
Answers:
a. Start executing the project since leadership is responsible for the business strategy.
b. Meet with the project sponsor to better understand the strategic bene๏ฌts of the project.
c. Propose an updated business case and project charter that is more aligned with the business strategy.
d. Conduct qualitative and quantitative risk analysis and record the results in the risk register.
A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended bene๏ฌts of the project align with the strategic objectives of the business.
What should the project manager do ๏ฌrst?
Answers:
a. Start executing the project since leadership is responsible for the business strategy.
b. Meet with the project sponsor to better understand the strategic bene๏ฌts of the project.
c. Propose an updated business case and project charter that is more aligned with the business strategy.
d. Conduct qualitative and quantitative risk analysis and record the results in the risk register.
๐1
If you have advanced knowledge and experience in risk management or if you are a project manager handling project risks including large-scale projects and/or complex environments, then PMI-RMP is an excellent choice for you.
The PMI Risk Management Professional (PMI-RMP) certification highlights your ability to identify and assess project risks, reduce threats and use opportunities. In this role, you improve and protect your organization's needs.
Sign up here: https://calendar.app.google/D4nJCrW48vLnnL4o9
More details here: KnowledgeMap.pm/exams/pricing
๐ Note:
All certifications of Marathon '25: KnowledgeMap.pm/Marathon
#risk #pmirmp #certification #pmi #projectmanagement #knowledgemap
Please open Telegram to view this post
VIEW IN TELEGRAM
๐4
Daily Question #2567
A Portfolio Manager is executing the Manage Portfolio Information process, and he is looking for the new components added to the portfolio as they may translate into new sets of stakeholders.
Where should he find this information in the first place?
A Portfolio Manager is executing the Manage Portfolio Information process, and he is looking for the new components added to the portfolio as they may translate into new sets of stakeholders.
Where should he find this information in the first place?
Answers #2567
Anonymous Quiz
33%
a. Portfolio Process Assets
11%
b. Portfolio
42%
c. Portfolio Management Plan
14%
d. Portfolio Component Reports
๐ค1
Daily Question #5328
A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?
A project manager is leading a project which shows a trend to exceed the cost baseline.
What should the project manager do first to manage the budget?
Anonymous Quiz
4%
a. Ask the project sponsor for assistance in getting the budget back on track.
82%
b. Meet with the project team to analyze the actual cost to determine deviations.
1%
c. Inform the stakeholders that the project will be finished over budget.
13%
d. Issue a change request including the analysis to increase the budget.
๐1
๐๐ป๐ผ๐๐น๐ฒ๐ฑ๐ด๐ฒ๐ ๐ฎ๐ฝ pinned ยซ๐ KnowledgeMap is Now Available by Subscription! ๐ Great news, friends! ๐ Weโve transitioned KnowledgeMap to a convenient subscription model, giving you unlimited access to all certification prep materials for just $9.99/month! ๐ฅ ๐ก What does this mean forโฆยป
Daily Question #2724
In your architectural organization, each program or project requires some specialized subject matter experts at certain time frames. Because of the interdependencies between components, often these SMEs are needed at the same time. Assume since this is a critical issue in the company, it invested in resource planning and allocating software, and dashboards can be prepared. The goal is to use these dashboard reports to:
In your architectural organization, each program or project requires some specialized subject matter experts at certain time frames. Because of the interdependencies between components, often these SMEs are needed at the same time. Assume since this is a critical issue in the company, it invested in resource planning and allocating software, and dashboards can be prepared. The goal is to use these dashboard reports to:
Daily Question #142
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis. The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
Answers:
a. Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.
b. Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.
c. Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.
d. Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis. The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
Answers:
a. Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.
b. Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.
c. Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.
d. Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.
๐1
๐ค1
Daily Question #5002
A global company hired a project manager for a new implementation at all of its sites. After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
A global company hired a project manager for a new implementation at all of its sites. After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
๐ค1
Daily Question #1153
In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a PV of $20,000 and an EV of $25,000, testing has a PV of $17,000 and EV of $15,000, and design has a PV of $34,000 and a EV of $42,000.
As a whole your project is:
In preparing for a team meeting you want to let the team know how they are doing on the project schedule over all. You calculate the task achievements as follows: planning has a PV of $20,000 and an EV of $25,000, testing has a PV of $17,000 and EV of $15,000, and design has a PV of $34,000 and a EV of $42,000.
As a whole your project is:
Daily Question #63
The project status meeting is not going well. Everyone is talking at the same time, there are people who are not participating, and many topics are being discussed at random.
Which of the following rules for effective meetings is NOT being adhered to?
The project status meeting is not going well. Everyone is talking at the same time, there are people who are not participating, and many topics are being discussed at random.
Which of the following rules for effective meetings is NOT being adhered to?
๐ค1
Hey everyone!
If you're not a fan of Telegram or have security concerns but still enjoy our daily questions, weโve got you covered!
๐ข Join our WhatsApp group here: https://chat.whatsapp.com/D9rnSipBWiZLPsqvW1wJl3
Also, feel free to share this link with friends and colleagues preparing for professional certifications who arenโt using Telegram. Letโs grow our learning community together! ๐
If you're not a fan of Telegram or have security concerns but still enjoy our daily questions, weโve got you covered!
๐ข Join our WhatsApp group here: https://chat.whatsapp.com/D9rnSipBWiZLPsqvW1wJl3
Also, feel free to share this link with friends and colleagues preparing for professional certifications who arenโt using Telegram. Letโs grow our learning community together! ๐
๐3