#PMP Question #911
Having taken over an "at-risk" project, you realize that many of the problems stem from shifting priorities, resource conflicts with other projects, and an on-again/off-again approach to the project.
These are classified as:
🔥1
#PMP Question #4310
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase. While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate.
How should the project manager address this issue?