#PMP Question #4713
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown above.
What should the team do next?
Answers:
a. Ask the product owner if some low-priority stories could be cut from the sprint.
b. Continue with the sprint as the progress shows buffers for potential interruptions.
c. Ask the project team to select any additional stories as they have additional capacity than planned.
d. Continue with the sprint work as planned and keep monitoring.
Answers #4713
Anonymous Quiz
4%
a
18%
b
21%
c
57%
d
👍1
#PMP Question #2734
During a project's initiation phase, a lessons-learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
Answers:
a. Discuss this issue with the project sponsor to request additional funding to implement mitigation.
b. Hire a construction management consultant to develop a comprehensive site execution plan.
c. Prequalify contractors with proven track records to eliminate productivity concerns.
d. Add construction productivity to the risk register and develop a mitigation strategy for site execution.
Answers #2734
Anonymous Quiz
5%
a
0%
b
5%
c
90%
d