#PMP Question #1359
You are the project manager of a new home construction project that will create 112 new homes with an average of 17 double hung windows in each home. A finish carpenter has complained that a recent shipment of prefabricated windows lack the brass sash pulls and locks that had been installed in all previous shipments. You contact the supplier who agrees to provide the hardware for the current and future shipments.
You determine:
Answers:
a. That further action is unnecessary at this time.
b. That the scope of the project has changed since additional time will be required to install the hardware.
c. That the supplier is in breach of contract.
d. That a change order requiring that window hardware be pre-installed should be sent to the window supplier.
Answers #1359
Anonymous Quiz
8%
a
23%
b
15%
c
54%
d