#PMP Question #3676
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Answers:
a. Provide a project management template for the project manager to follow as a guide.
b. Suggest using an agile approach since customer and team collaboration is critical for project success.
c. Work with the project manager to develop a new approach that will bring benefits to the project.
d. Establish a project management methodology that requires the customer to provide daily updates to the team.
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Answers:
a. Provide a project management template for the project manager to follow as a guide.
b. Suggest using an agile approach since customer and team collaboration is critical for project success.
c. Work with the project manager to develop a new approach that will bring benefits to the project.
d. Establish a project management methodology that requires the customer to provide daily updates to the team.
What is the standard processing time for an online PMI-PBA certification application, and what exception might affect this timeline?
Referer to:https://knowledgemap.pm/certifications/pba/certification-process/review/
#PMIPBA #Certification #PMI
Referer to:https://knowledgemap.pm/certifications/pba/certification-process/review/
#PMIPBA #Certification #PMI
KnowledgeMap
PMI-PBA Application Timeline
Discover the PMI-PBA Application Timeline, including standard processing times and how audits may impact your application review.
👍2
#PMP Question #1359
You are the project manager of a new home construction project that will create 112 new homes with an average of 17 double hung windows in each home. A finish carpenter has complained that a recent shipment of prefabricated windows lack the brass sash pulls and locks that had been installed in all previous shipments. You contact the supplier who agrees to provide the hardware for the current and future shipments.
You determine:
Answers:
a. That further action is unnecessary at this time.
b. That the scope of the project has changed since additional time will be required to install the hardware.
c. That the supplier is in breach of contract.
d. That a change order requiring that window hardware be pre-installed should be sent to the window supplier.
You are the project manager of a new home construction project that will create 112 new homes with an average of 17 double hung windows in each home. A finish carpenter has complained that a recent shipment of prefabricated windows lack the brass sash pulls and locks that had been installed in all previous shipments. You contact the supplier who agrees to provide the hardware for the current and future shipments.
You determine:
Answers:
a. That further action is unnecessary at this time.
b. That the scope of the project has changed since additional time will be required to install the hardware.
c. That the supplier is in breach of contract.
d. That a change order requiring that window hardware be pre-installed should be sent to the window supplier.
Why is seeking early feedback essential in agile project delivery, and how can agile teams effectively implement it?
Referer to:https://knowledgemap.pm/certifications/acp/domain-4-delivery/acp-seek-early-feedback/
#Agile #Delivery #PMIACP
Referer to:https://knowledgemap.pm/certifications/acp/domain-4-delivery/acp-seek-early-feedback/
#Agile #Delivery #PMIACP
KnowledgeMap
PMI-ACP Seek Early Feedback
Learn how to seek early feedback in agile development to improve customer satisfaction, reduce rework, and deliver real value.
👍1