#PMP Question #4912
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
Answers:
a. Use the team's connections with international colleagues to get early warnings on future changes.
b. Keep the focus on the priority items while the change goes through the change control process.
c. Reject the change request since it may negatively impact the project's performance.
d. Implement the change request as soon as possible to avoid accumulating new scope.
Answers #4912
Anonymous Quiz
19%
a
69%
b
4%
c
8%
d
👍1
What is the relationship between Business Analysis and Project Management processes according to the Standard for Business Analysis in the PMI-PBA certification, and how do their process groups align throughout the project lifecycle?

Referer to:https://knowledgemap.pm/certifications/pba/run-in/standard/

#PMIPBA #BusinessAnalysis #ProjectManagement
👍1
#PMP Question #142
A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis. The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?
Answers:
a. Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.
b. Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.
c. Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.
d. Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.
Answers #142
Anonymous Quiz
8%
a
42%
b
0%
c
50%
d
🤔1
#PMP Question #5344
A customer calls the project manager to express concern about a project team member who has been making changes within the live environment without approval. The team member mentioned that the customer called and asked them to make the changes.
What should the project manager do next?
Answers:
a. Reinforce the value of documenting and approving all change requests and ask the customer to issue these through the agreed channels.
b. Organize a meeting to mediate the relationship between the customer and the team member to ensure no feelings are hurt.
c. Ask the customer to email all requests directly to you and you will ensure they are actioned by the correct team member.
d. Explain to the customer that the team member was just trying to help and the changes can be reverted if necessary.
👍1
#PMP Question #1730
A difference between a statement of work and a scope statement is:
Answers:
a. The statement of work is prepared by the customer while the scope statement is developed by the project management team.
b. The statement of work focuses on physical or technical matters, while the project scope statement focuses on a functional view.
c. The project scope statement is in most projects developed before the statement of work is written.
d. A project scope statement can become a contract document; a statement of work cannot.
Answers #1730
Anonymous Quiz
37%
a
30%
b
11%
c
22%
d
👍1
#PMP Question #3500
A project manager works at an organization that is transitioning to Agile. The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
Answers:
a. Advise the project management office (PMO) to use the burndown chart as the single communication channel.
b. Develop a communications management plan for each category in the stakeholder register.
c. Include the burndown chart in a monthly report that is distributed to all stakeholders.
d. Postpone the recommendation since the organization does not currently have a defined agile methodology.
Answers #3500
Anonymous Quiz
0%
a
50%
b
45%
c
5%
d
🤔1
Join Our October PMI-CP Prep Group!
Training Starts Soon – You Still Have Time to Enroll!

The PMI-CP is the only globally recognized certification tailored for construction professionals, providing essential skills in project leadership, contract management, and lean practices to boost career growth and sustainability.

About the Preparation Course:
- Price: €499*
- Duration: 2 months
- Mentor: Yana Bazylevska, PMP, PMI-CP
- Full access to the KnowledgeMap platform included.

We will be holding an open onboarding on October 7 at 18:00 (Kyiv Time).
🔗Add to your calendar: https://calendar.app.google/WZMF2zPpaNofVbFX9
Also join our PMI-CP chat here. ❤️📱

Got Questions?
Ask
@AnatoliiSavin - Founder & Chief Mentor of KnowledgeMap is here to guide your certification journey. Reach out for expert advice and personalized mentoring!

*Ways to Save :
- Education is free for Ukrainian veterans and military personnel.
- Pay in 2-3 installments for easier budgeting.
- Pay in full by October 7 for a 20% discount.
- Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
- For PMI Ukraine members: additional 10% discount.

📌 Note:
- The next PMI-CP Prep group is planned for April 2026.
- Mentor-to-Mentor Course begins on October 21, 2025.
All certifications of Marathon '25
- KnowledgeMap.pm/Marathon

Please also join the certifications preparation channels:
📱 Telegram: t.me/KnowledgeMap
📱 WhatsApp: chat.whatsapp.com/D9rnSipBWiZLPsqvW1wJl3
📱 LinkedIn: linkedin.com/company/knowledge-map
Please open Telegram to view this post
VIEW IN TELEGRAM
🔥1
#PMP Question #3676
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
Answers:
a. Provide a project management template for the project manager to follow as a guide.
b. Suggest using an agile approach since customer and team collaboration is critical for project success.
c. Work with the project manager to develop a new approach that will bring benefits to the project.
d. Establish a project management methodology that requires the customer to provide daily updates to the team.