#PMP Question #1116
Valid reasons for considering termination of a project include all of the following except:
Answers:
a. The scope of the project is found to be inconsistent with the organizationโ€™s financial strength.
b. Organizational support is being spread among too many projects.
c. Scope change requests are numerous and continuous.
d. The project product has become available as a commercial off the shelf product.
#CAPM Question #151
A project manager has received activity duration estimates from his team.
Which of the following does he need in order to complete the Develop Schedule process?
Anonymous Quiz
18%
a. Change requests.
29%
b. Schedule change control system.
15%
c. Recommended corrective actions.
38%
d. Reserves.
๐Ÿค”1
#PMP Question #5152
The project manager for a defense software application has a culturally and gender-diverse team with a short project timeline.
Considering the project will be stressful, what skill should the project manager use to monitor the team's performance?
#PMP Question #2978
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?
#PMP Question #4912
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
Answers:
a. Use the team's connections with international colleagues to get early warnings on future changes.
b. Keep the focus on the priority items while the change goes through the change control process.
c. Reject the change request since it may negatively impact the project's performance.
d. Implement the change request as soon as possible to avoid accumulating new scope.