#PMP Question #1116
Valid reasons for considering termination of a project include all of the following except:
Answers:
a. The scope of the project is found to be inconsistent with the organizationโ€™s financial strength.
b. Organizational support is being spread among too many projects.
c. Scope change requests are numerous and continuous.
d. The project product has become available as a commercial off the shelf product.
#CAPM Question #151
A project manager has received activity duration estimates from his team.
Which of the following does he need in order to complete the Develop Schedule process?
Anonymous Quiz
20%
a. Change requests.
29%
b. Schedule change control system.
14%
c. Recommended corrective actions.
37%
d. Reserves.
๐Ÿค”1
#PMP Question #5152
The project manager for a defense software application has a culturally and gender-diverse team with a short project timeline.
Considering the project will be stressful, what skill should the project manager use to monitor the team's performance?
#PMP Question #2978
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?