#ISO21502 Question #1308
Which method integrates scope, actual cost, budget, and schedule for assessment of progress and performance?
Anonymous Quiz
15%
a. Variance analysis
66%
b. Earned value management
0%
c. Trend analysis
20%
d. Work performance report
๐Ÿ‘2
#PMP Question #2743
A construction project to build a ๏ฌsh hatchery is in execution. The operations group noti๏ฌed the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
We found about 1,000 questions on Knowledge Map that correspond to the principles of project management described in the draft of PMBOK Guide - 8th Edition.
So, while you are preparing for the exam based on the current PMP ECO, you are also checking how well you know the first part of the upcoming PMBOK.
๐Ÿ”ฅ1
Join Our September PMP Certification Preparation Group!
Prepare for the PMP exam now โ€” while the current PMP Exam Outline 2021 is still valid!
Note: The new PMBOK Guide โ€“ 8th Edition is expected in January 2026. Use this window to certify before the exam updates.
- Cost: โ‚ฌ750
- Duration: 3 months
- Certificate: 35 contact hours
- Platform Access: Full access to KnowledgeMap
- Support: Mentoring and expert guidance every step of the way

๐Ÿ“… Open Onboarding Session: September 23 at 18:00 (Kyiv Time)
Add to your calendar: https://calendar.app.google/vV7eWz7fUNMVvsMR6

๐Ÿ’ก Ways to Save:
- Free training for Ukrainian veterans and military personnel
- Flexible payment: split the cost into 2 or 3 installments
- Early bird: Pay in full by September 23 and get 20% off
- PMI Ukraine Chapter members: Get an additional 10% discount

๐Ÿ“Œ Mark Your Calendar:
- Next PMP Group: Starts November 4, 2025
- PMI-CP (construction): Starts October 7
- Mentor-to-Mentor Course: Starts October 21
Full calendar: KnowledgeMap.pm/Marathon
๐Ÿ”ฅ1
#PMP Question #1116
Valid reasons for considering termination of a project include all of the following except:
Answers:
a. The scope of the project is found to be inconsistent with the organizationโ€™s financial strength.
b. Organizational support is being spread among too many projects.
c. Scope change requests are numerous and continuous.
d. The project product has become available as a commercial off the shelf product.