#PMP Question #1151
During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for an additional budget.
What should the project manager do first?
For the First Time in Ukraine!
Artificial Intelligence Certification Training for Project Managers - Cognitive Project Management in AI (CPMAI)โ„ข v7.

About the Course:
Cost: โ‚ฌ490 (PMI fee not included)
Duration: 2 months
Access: Full access to the Knowledge Map
Support: Mentoring and guidance throughout your CPMAI journey

Open Onboarding Session:
Date: August 26, 18:00 (Kyiv time)
Join here: https://calendar.app.google/scXppfXkdHe6JfdA8

Ways to Save:
- Free enrollment for Ukrainian veterans and military personnel
- Flexible installment payments (2โ€“3 parts)
- 10% discount for full payment by August 26
- Extra 5% discount for PMI Ukraine Chapter members

Note:
- The next CPMAI group is scheduled for Februaryโ€“March 2026
- PgMP (programs) starts: September 8
- PMP (projects) starts: September 22
๐Ÿ“… Check the full Certification Calendar 2025โ€“26: KnowledgeMap.pm/Marathon
๐Ÿ‘1
#PMP Question #3654
An agile project team is tasked with a new project. After multiple discussions with the customer, it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase.
What should the team do next?
Answers:
a. Start with the end user documentation review with the customer and gather feedback.
b. Start with the design of the prototype review with the customer and gather feedback.
c. Start with the product prototype development, review with the customer, and gather feedback.
d. Start with the product architecture review with the customer and gather feedback.
#ISO21502 Question #1415
Which tool includes the integrated procedures, such as configuration management, for authorizing cost baseline changes?
Anonymous Quiz
25%
a. Cost management plan
69%
b. Change control tools
6%
c. Budget updates
0%
d. Performance reports
#PMP Question #3311
A project manager has just finished planning for a project when the client adds a new project team member. The project manager knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment but is slow to respond otherwise.
How should the project manager reflect this in their planning?
Answers:
a. Send out recurring onsite project meeting invites to ensure the team member's presence.
b. Update the project charter to include the new team member for this project.
c. Monitor the new team member's input to gauge their value to the project.
d. Include the team member in the stakeholder register and update the communications management plan.