#CAPM Question #4338
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
We are preparing a new certification course on the Knowledge Map โ€” CPMAIโ„ข v7: Cognitive Project Management for AI.
Since PMI acquired this certification along with the company Cognilytica, they now provide extensive training video materials. Unfortunately, there are far too many of them. While some are helpful, many are overly long, repetitive, and not very engaging.
However, you canโ€™t skip this course โ€” itโ€™s mandatory for certification and already included in the price.

Thatโ€™s why our approach for this certification is more streamlined:
1. Assess your current knowledge and identify gaps to close.
2. Create a personalized certification roadmap with both administrative and training steps.
3. Provide access to our question bank.
4. Share practical tips and life hacks to make obtaining the certificate easier and more likely.

Naturally, PMI never discloses the actual exam questions. However, for CPMAI, they did publish 15 Sample Questions in the CPMAI Exam Content Outline.

Using these sample questions, along with other CPMAI study materials, we trained an AI model to generate a question bank that allows you to test and improve your knowledge for a higher chance of passing the exam.

You can take the Preliminary CPMAI Test right now to see where you stand:
๐Ÿ”— https://knowledgemap.pm/certifications/cpmai
Are you ready?
๐Ÿ”ฅ3โค1
#PMP Question #1151
During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for an additional budget.
What should the project manager do first?
For the First Time in Ukraine!
Artificial Intelligence Certification Training for Project Managers - Cognitive Project Management in AI (CPMAI)โ„ข v7.

About the Course:
Cost: โ‚ฌ490 (PMI fee not included)
Duration: 2 months
Access: Full access to the Knowledge Map
Support: Mentoring and guidance throughout your CPMAI journey

Open Onboarding Session:
Date: August 26, 18:00 (Kyiv time)
Join here: https://calendar.app.google/scXppfXkdHe6JfdA8

Ways to Save:
- Free enrollment for Ukrainian veterans and military personnel
- Flexible installment payments (2โ€“3 parts)
- 10% discount for full payment by August 26
- Extra 5% discount for PMI Ukraine Chapter members

Note:
- The next CPMAI group is scheduled for Februaryโ€“March 2026
- PgMP (programs) starts: September 8
- PMP (projects) starts: September 22
๐Ÿ“… Check the full Certification Calendar 2025โ€“26: KnowledgeMap.pm/Marathon
๐Ÿ‘1
#PMP Question #3654
An agile project team is tasked with a new project. After multiple discussions with the customer, it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase.
What should the team do next?
Answers:
a. Start with the end user documentation review with the customer and gather feedback.
b. Start with the design of the prototype review with the customer and gather feedback.
c. Start with the product prototype development, review with the customer, and gather feedback.
d. Start with the product architecture review with the customer and gather feedback.