#PMP Question #4646
A project manager presented the project schedule to the main stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?
Answers:
a. Hold a stakeholder meeting to align timelines and scope expectations.
b. Crash the schedule to shorten the timeline while keeping the scope unchanged.
c. Update the cost management plan to allocate more resources to the project to finish the scope earlier.
d. Reduce the scope of the project by removing activities and shortening the timeline.
A project manager presented the project schedule to the main stakeholders. They have requested that the project be completed two months earlier than the scheduled date.
What should the project manager do?
Answers:
a. Hold a stakeholder meeting to align timelines and scope expectations.
b. Crash the schedule to shorten the timeline while keeping the scope unchanged.
c. Update the cost management plan to allocate more resources to the project to finish the scope earlier.
d. Reduce the scope of the project by removing activities and shortening the timeline.
๐1
What are the key enablers and resources needed to learn the Manage Communications task for PMP certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-2-manage-communications/
#PMP #ManageCommunications #ProjectManagementTips
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-2-manage-communications/
#PMP #ManageCommunications #ProjectManagementTips
KnowledgeMap
PMP Manage Communications
Master PMP Manage Communications with key enablers and resources for successful project communication in PMP certification.
๐1
#PfMP Question #2102
The Defining Process Group is most active:
The Defining Process Group is most active:
Anonymous Quiz
9%
a. At the time the organization identifies and updates its plans
14%
b. At the time the organization identifies and updates its strategic goals
3%
c. At the time the organization identifies and updates its near term budgets
74%
d. All of the answer choices
How long does it take to process a CAPM certification application?
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/application-review/
#CAPM #PMI #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/application-review/
#CAPM #PMI #ProjectManagement
KnowledgeMap
CAPM Application Review
The application review for the CAPM certification takes 24 hours unless selected for an audit. Share your experience with the review process!
๐2
#PfMP Question #1995
Glenn is currently involved in the Authorize Portfolio process. He is describing to you a tool and technique he is currently applying which identifies which portfolio components have been assigned resources. What is Glenn describing?
Glenn is currently involved in the Authorize Portfolio process. He is describing to you a tool and technique he is currently applying which identifies which portfolio components have been assigned resources. What is Glenn describing?
What key aspects of test management are covered in the "Managing the Test Activities" chapter of the ISTQB CTFL Certification, and how do they contribute to effective software testing?
Referer to:https://knowledgemap.pm/certifications/ctfl/managing-the-test-activities/
#TestManagement #ISTQB #CTFL #SoftwareTesting
Referer to:https://knowledgemap.pm/certifications/ctfl/managing-the-test-activities/
#TestManagement #ISTQB #CTFL #SoftwareTesting
KnowledgeMap
ISTQB CTFL Managing Test Activities
Learn about managing test activities in ISTQB CTFL, covering test planning, risk management, defect management, and test monitoring.
๐2
#CAPM Question #5244
A new sales software development project is underway. The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.
Which project approach should the project manager take?
A new sales software development project is underway. The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.
Which project approach should the project manager take?
What should you expect if your PMI-RMP certification application is selected for an audit, and what steps must you take to comply?
Referer to:https://knowledgemap.pm/certifications/rmp/certification-process/audit-process/
#PMIRMP #Certification #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/rmp/certification-process/audit-process/
#PMIRMP #Certification #ProjectManagement
KnowledgeMap
PMI-RMP Audit Process
Learn what to expect from the PMI-RMP Certification Audit Process, including required documents, timelines, and how to prepare.
๐ฅ1
#PMI-CP Question #4310
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase. While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate.
How should the project manager address this issue?
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase. While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate.
How should the project manager address this issue?
What are the steps and payment options for submitting the payment for CAPM certification after my application is processed?
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/capm-payment-submission-process/
#CAPM #PaymentProcess #PMI #Certification
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/capm-payment-submission-process/
#CAPM #PaymentProcess #PMI #Certification
KnowledgeMap
CAPM Payment Submission Process
Discover the steps for the CAPM payment submission process through PMIโs online system. Find valid payment methods in the CAPM Handbook.
๐1
#CAPM Question #1756
The smallest amount of functionality that delivers customer value is best described as a:
The smallest amount of functionality that delivers customer value is best described as a:
Anonymous Quiz
15%
a. Function point analysis
26%
b. Right sized story
49%
c. Minimum marketable feature
10%
d. User story map
How does PMI membership support candidates in preparing for the PMI-ACPยฎ certification exam?
Referer to:https://knowledgemap.pm/certifications/acp/introduction-to-the-pmi-acp-prep-course/become-a-pmi-member/
#PMI #PMIACP #AgileCertification
Referer to:https://knowledgemap.pm/certifications/acp/introduction-to-the-pmi-acp-prep-course/become-a-pmi-member/
#PMI #PMIACP #AgileCertification
KnowledgeMap
PMI-ACP benefits of PMI membership
PMI-ACP certification benefits of PMI membership include exclusive resources, discounts, and networking to boost your exam prep and career.
๐2
#PMP Question #645
Earned value analysis is an example of:
Earned value analysis is an example of:
Anonymous Quiz
61%
a. Performance reporting
14%
b. Planning control
3%
c. Ishikawa diagrams
22%
d. Integrating the project components into a whole
๐1
What are the fundamental concepts and processes in software testing covered in the ISTQB CTFL โFundamentals of Testingโ chapter?
Referer to:https://knowledgemap.pm/certifications/ctfl/fundamentals-of-testing/
#SoftwareTesting #ISTQB #CTFL #TestingFundamentals
Referer to:https://knowledgemap.pm/certifications/ctfl/fundamentals-of-testing/
#SoftwareTesting #ISTQB #CTFL #TestingFundamentals
KnowledgeMap
ISTQB CTFL Fundamentals of Testing
Learn the fundamentals of testing for ISTQB CTFL, including test concepts, processes, principles, and essential skills.
๐2
#PMP Question #3874
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy.
How should the project manager reflect this change in the project?
Answers:
a. Update the communication styles for enrolled team members in the communications management plan.
b. Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM).
c. Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.
d. Update the resource calendar for enrolled team members in the resource management plan.
During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy.
How should the project manager reflect this change in the project?
Answers:
a. Update the communication styles for enrolled team members in the communications management plan.
b. Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM).
c. Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.
d. Update the resource calendar for enrolled team members in the resource management plan.
๐1