Answers #2014
Anonymous Quiz
46%
a
11%
b
20%
c
23%
d
🔥1
#CAPM Question #1876
The Scrum Master and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the Scrum Master should take is to ask:
Anonymous Quiz
78%
a. The Product Owner to clarify the requirement.
5%
b. The business owner to resolve the problem.
17%
c. The business analyst to research the product value.
0%
d. Another project manager how to resolve the problem.
#PMP Question #5421
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
Answers:
a. Create a lessons learned register to include operations team training for future projects.
b. Include knowledge transfer sessions between the project and operations teams at every stage.
c. Change the project management plan to add a final stage for product handoff to the operations team.
d. Prepare detailed documentation to be shared with the operations team during project closure.
#PMP Question #2980
A project manager Is transitioning from a predictive live cycle project to a new agile project.
How should the project manager manage and control the scope of the new project?
Answers:
a. Create a scope baseline and put the rest as backlog activities.
b. Estimate the work the team can complete and define story sizes to keep the project under control.
c. Develop a plan to complete more work In less time.
d. Spend a short amount of time defining the scope and building prototypes to refine the requirements.
Answers #2980
Anonymous Quiz
18%
a
43%
b
2%
c
37%
d
🤔2
#PMP Question #5444
A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.
What should the project manager do next?
Anonymous Quiz
14%
a. Assign the tasks to the resources based on their expertise.
37%
b. Ensure that the priority of each task is clear to the team.
46%
c. Ask the team to self-organize and manage the work assigned.
3%
d. Tell the team which task to focus on at the next daily standup.
🔥1
#PMP Question #4935
A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.
How should the project manager proceed in order to complete the risk register?