#PMP Question #5196
A project manager is working on a project with multiple workstreams. One of the workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen again?
A project manager is working on a project with multiple workstreams. One of the workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen again?
April 13
April 13
What knowledge and skills are required to learn the Project Scope Management task for the CAPM certification?
Referer to:https://knowledgemap.pm/certifications/capm/guide-learning/scope/
#ProjectScopeManagement #CAPM #Certification #PMBOK
Referer to:https://knowledgemap.pm/certifications/capm/guide-learning/scope/
#ProjectScopeManagement #CAPM #Certification #PMBOK
KnowledgeMap
Scope Management Exam - KnowledgeMap
buy exam Scope Management Exam on KnowledgeMap
April 13
#CPCM Question #7349
What is a "Contractual Extension"?
What is a "Contractual Extension"?
Anonymous Quiz
55%
a. An agreement to prolong the duration of the contract beyond
23%
b. A formal change to the contract terms.
4%
c. A financial penalty for late performance.
17%
d. A document detailing the scope of work.
April 14
What are the key steps and resources involved in ensuring that team members and stakeholders are adequately trained for PMP Certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-5-ensure-team-members-stakeholders-are-adequately-trained/
#PMP #ProjectManagementExcellence #StakeholderDevelopment
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-5-ensure-team-members-stakeholders-are-adequately-trained/
#PMP #ProjectManagementExcellence #StakeholderDevelopment
KnowledgeMap
PMP Team Members Stakeholders Training
Explore The PMP Team Members Stakeholders Training task and key enablers to ensure effective training and development for your project team.
April 14
#PMP Question #5343
A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and sustained?
A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and sustained?
April 15
April 15
What should you share after passing the PMPCertification exam?
Referer to:https://knowledgemap.pm/certifications/pmp/domains/pmp-exam/
#PMP #Certification #PassTheExam #ShareYourJourney
Referer to:https://knowledgemap.pm/certifications/pmp/domains/pmp-exam/
#PMP #Certification #PassTheExam #ShareYourJourney
KnowledgeMap
PMP Certification Exam
Pass the PMP Certification Exam and share your experience in the comments to inspire and guide future candidates!
April 15
๐๐ป๐ผ๐๐น๐ฒ๐ฑ๐ด๐ฒ๐ ๐ฎ๐ฝ
Still deciding whether to join the PMI-PBA Prep Group? Here's a great reason to say yes!
Your mentor for this training will be Denis Gobov ( @Dgobov ):
- Business analyst and trainer withโฏmore than 20 โฏyears of experience.
- Head of Business Analysis Capability at DataArt
- Editor at artofba.com/blog
- The co-author of the certification exam for CBAP based on BABOK 3.0.
- The first Ukrainian analyst who passed certification exams from leading organizations in business analysis and requirement engineering areas: CBAP (IIBA), PMI-PBA (PMI), CPRE (IREB).
- PhD
- Winner of the award "Best professional in the field of business analysis in 2013 and 2016โ, IT Ukraine Association and "The Best Business Analyst in 2017", ITNetwork
โ Register for the free onboarding session: calendar.app.google/KvpVeiefSr1MNjAJA
๐ฌ Join the group chat on Telegram: t.me/+4kd3mhEDQS5lOTI6
Letโs get you PBA-ready! ๐ผ๐
Your mentor for this training will be Denis Gobov ( @Dgobov ):
- Business analyst and trainer withโฏmore than 20 โฏyears of experience.
- Head of Business Analysis Capability at DataArt
- Editor at artofba.com/blog
- The co-author of the certification exam for CBAP based on BABOK 3.0.
- The first Ukrainian analyst who passed certification exams from leading organizations in business analysis and requirement engineering areas: CBAP (IIBA), PMI-PBA (PMI), CPRE (IREB).
- PhD
- Winner of the award "Best professional in the field of business analysis in 2013 and 2016โ, IT Ukraine Association and "The Best Business Analyst in 2017", ITNetwork
โ Register for the free onboarding session: calendar.app.google/KvpVeiefSr1MNjAJA
๐ฌ Join the group chat on Telegram: t.me/+4kd3mhEDQS5lOTI6
Letโs get you PBA-ready! ๐ผ๐
April 15
#CAPM Question #65
Integrated change control is concerned with all of the following except:
Integrated change control is concerned with all of the following except:
Anonymous Quiz
16%
a. Determining that a change has occurred
13%
b. Managing changes as they occur
18%
c. Creating change requests
53%
d. Influencing factors that create change to ensure that changes are beneficial
April 16
How can taking the CTFL Mock Exam help in preparing for the ISTQB CTFL certification?
Referer to:https://knowledgemap.pm/certifications/ctfl/take-ctfl-mock-exam/
#CTFL #MockExam #ISTQB #Certification #SoftwareTesting
Referer to:https://knowledgemap.pm/certifications/ctfl/take-ctfl-mock-exam/
#CTFL #MockExam #ISTQB #Certification #SoftwareTesting
KnowledgeMap
CTFL Mock Exam for ISTQB Certification
Prepare for the ISTQB CTFL certification with the CTFL Mock Exam. Test your knowledge, review key concepts, and improve your exam performance.
April 16
#CPCM Question #7873
What is the primary purpose of a Contract Performance
What is the primary purpose of a Contract Performance
Anonymous Quiz
67%
a. To evaluate and report on contractor performance and compliance
20%
b. To negotiate contract terms and conditions
2%
c. To develop new contract proposals
12%
d. To manage project budgets
April 17
What are the key test techniques covered in the 'Test Analysis and Design' chapter of the ISTQB CTFL certification, and how do they contribute to effective test case creation?
Referer to:https://knowledgemap.pm/certifications/ctfl/test-analysis-and-design/
#SoftwareTesting #ISTQB #CTFL #TestDesign
Referer to:https://knowledgemap.pm/certifications/ctfl/test-analysis-and-design/
#SoftwareTesting #ISTQB #CTFL #TestDesign
KnowledgeMap
ISTQB CTFL Test Analysis and Design
Explore ISTQB CTFL Test Analysis and Design, focusing on black-box, white-box, and experience-based techniques for test case creation.
April 17
#PMI-RMP Question #1546
One of the risks identi๏ฌed during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
One of the risks identi๏ฌed during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
April 18
April 18
What resources and enablers are necessary for effectively learning and applying the Assess and Manage Risks task in project management according to the PMP certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-3-assess-and-manage-risks/
#RiskManagement #PMP #ProjectManagementResources
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-3-assess-and-manage-risks/
#RiskManagement #PMP #ProjectManagementResources
KnowledgeMap
PMP Assess and Manage Risks
Learn essential resources and enablers for the PMP Assess and Manage Risks task to boost your project management skills and exam preparation.
April 18
#PfMP Question #2463
How is "Change" defined for portfolio management?
How is "Change" defined for portfolio management?
Anonymous Quiz
11%
a. Depending on organizations, it can be a random process
61%
b. Occurs in the broader internal and external environment monitored by the manager
11%
c. Strictly internal controls that are monitored by the manager
18%
d. Occurs in the broader internal and external environment but not necessarily monitored
April 19
What are the key responsibilities and resources involved in ensuring knowledge transfer for project continuity in the PMP Certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-16-ensure-knowledge-transfer-for-project-continuity/
#KnowledgeTransfer #ProjectContinuity #PMP
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-16-ensure-knowledge-transfer-for-project-continuity/
#KnowledgeTransfer #ProjectContinuity #PMP
KnowledgeMap
PMP Ensure Knowledge Transfer for Project Continuity
Learn how to ensure knowledge transfer for project continuity in PMP Certification with key resources and strategies for success.
April 19
#PfMP Question #2245
A portfolio team member is confused about what is meant by organizational resources. Which of the following is possibly one of the organizational resources?
A portfolio team member is confused about what is meant by organizational resources. Which of the following is possibly one of the organizational resources?
Anonymous Quiz
3%
a. Funds
16%
b. Tangible and intangible assets
15%
c. Program and project managers and subject matter experts
66%
d. All the options
April 20
#PMP Question #4964
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected.
What should the project manager do?
Answers:
a. Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project.
b. Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes.
c. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
d. Explain that the distribution of important news can only be done using traceable communication methods.
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected.
What should the project manager do?
Answers:
a. Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project.
b. Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes.
c. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
d. Explain that the distribution of important news can only be done using traceable communication methods.