#PMP Question #118
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
#PMP Question #748
The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables.
Which of the following would be the BEST choice for getting your project better organized?
#PMP Question #2987
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed-upon hours no longer work due to the team member's personal commitments.
What should the project manager do?
#PMP Question #1704
Which statement is false?
Progressive elaboration of project scopeโ€ฆ
Answers:
a. โ€ฆis a characteristic of projects that accompanies the concepts of temporary and unique.
b. โ€ฆmeans developing in steps. It not should be confused with scope creep.
c. โ€ฆsignals a weak spot in the scope definition process, caused by incomplete contracts and specifications.
d. โ€ฆwhen properly managed, integrates elaboration of project and deliverable specifications.
#PMP Question #5359
During the planning for a long project, the project manager recognized that several members of the team are new to their roles.
How should the project manager incorporate this into planning?
Answers:
a. Increase the overall project duration to account for the inexperienced team members on the project.
b. Ensure planning has accounted for replacing team members in new project roles who do not deliver on project goals.
c. Assess the training requirements and ensure time for professional development training by senior members.
d. Revisit the project resource allocation to remove the inexperienced team members assigned to the project.