#PMP Question #118
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
#PMP Question #412
During which risk management process is a determination to transfer a risk made?
During which risk management process is a determination to transfer a risk made?
Anonymous Quiz
11%
a. Identify Risks.
19%
b. Perform Quantitative Risk Analysis.
58%
c. Plan Risk Responses.
11%
d. Monitor Risks.
#PMP Question #748
The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables.
Which of the following would be the BEST choice for getting your project better organized?
The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables.
Which of the following would be the BEST choice for getting your project better organized?
What benefit is offered for the remaining exams after passing the exams in the People Domain for the PMP certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/pmp-process-domain-exam-preparation/
#PMP #MentoringDiscount #Exams
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/pmp-process-domain-exam-preparation/
#PMP #MentoringDiscount #Exams
KnowledgeMap
PMP Process Domain Exam Preparation
Boost your PMP Process Domain exam preparation and get discounts on mentoring, plus free exams for continued success.
๐2
#PMP Question #5317
A team is developing an experimental program to be used by the public.
What should the project manager do to ensure the desired benefits are achieved?
A team is developing an experimental program to be used by the public.
What should the project manager do to ensure the desired benefits are achieved?
Anonymous Quiz
14%
a. Ensure that the project team fully tests the program.
61%
b. Ensure a review is done with a representative group of users.
11%
c. Meet with government officials to review policy requirements.
14%
d. Document the features fully and update the specifications.
#PMP Question #2987
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed-upon hours no longer work due to the team member's personal commitments.
What should the project manager do?
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed-upon hours no longer work due to the team member's personal commitments.
What should the project manager do?
What steps should be taken to successfully negotiate project agreements, according to the PMP Certification guidelines?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-8-negotiate-project-agreements/
#ProjectAgreements #PMP #NegotiationSkills
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-8-negotiate-project-agreements/
#ProjectAgreements #PMP #NegotiationSkills
KnowledgeMap
PMP Negotiate Project Agreements
Learn key strategies to negotiate project agreements and succeed in PMP certification with essential resources and techniques.
๐2
#PMP Question #1704
Which statement is false?
Progressive elaboration of project scopeโฆ
Answers:
a. โฆis a characteristic of projects that accompanies the concepts of temporary and unique.
b. โฆmeans developing in steps. It not should be confused with scope creep.
c. โฆsignals a weak spot in the scope definition process, caused by incomplete contracts and specifications.
d. โฆwhen properly managed, integrates elaboration of project and deliverable specifications.
Which statement is false?
Progressive elaboration of project scopeโฆ
Answers:
a. โฆis a characteristic of projects that accompanies the concepts of temporary and unique.
b. โฆmeans developing in steps. It not should be confused with scope creep.
c. โฆsignals a weak spot in the scope definition process, caused by incomplete contracts and specifications.
d. โฆwhen properly managed, integrates elaboration of project and deliverable specifications.
What benefit is offered for the remaining exams after passing the exams in the People Domain for the PMP certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/pmp-process-domain-exam-preparation/
#PMP #MentoringDiscount #Exams
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/pmp-process-domain-exam-preparation/
#PMP #MentoringDiscount #Exams
KnowledgeMap
PMP Process Domain Exam Preparation
Boost your PMP Process Domain exam preparation and get discounts on mentoring, plus free exams for continued success.
๐2
#PMP Question #5359
During the planning for a long project, the project manager recognized that several members of the team are new to their roles.
How should the project manager incorporate this into planning?
Answers:
a. Increase the overall project duration to account for the inexperienced team members on the project.
b. Ensure planning has accounted for replacing team members in new project roles who do not deliver on project goals.
c. Assess the training requirements and ensure time for professional development training by senior members.
d. Revisit the project resource allocation to remove the inexperienced team members assigned to the project.
During the planning for a long project, the project manager recognized that several members of the team are new to their roles.
How should the project manager incorporate this into planning?
Answers:
a. Increase the overall project duration to account for the inexperienced team members on the project.
b. Ensure planning has accounted for replacing team members in new project roles who do not deliver on project goals.
c. Assess the training requirements and ensure time for professional development training by senior members.
d. Revisit the project resource allocation to remove the inexperienced team members assigned to the project.