#CAPM Question #3784
When controlling a schedule what data analysis technique would NOT be used?
When controlling a schedule what data analysis technique would NOT be used?
Anonymous Quiz
31%
a. Performance reviews.
22%
b. Iteration burndown charts.
18%
c. Earned value analysis.
29%
d. Schedule change control
👏1
#CAPM Question #1876
The Scrum Master and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the Scrum Master should take is to ask:
The Scrum Master and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the Scrum Master should take is to ask:
Anonymous Quiz
80%
a. The Product Owner to clarify the requirement.
5%
b. The business owner to resolve the problem.
16%
c. The business analyst to research the product value.
0%
d. Another project manager how to resolve the problem.
What are the key steps involved in preparing and executing task management in Agile project management, and how can tasks be prioritized based on their success criteria and impact on project success?
Referer to:https://knowledgemap.pm/certifications/capm/agile-frameworks-methodologies-and-methodologies-for-capm-certification/5-determine-how-to-prepare-and-execute-agile-task-management-steps/
#AgileProjectManagement #TaskPrioritization #CAPM
Referer to:https://knowledgemap.pm/certifications/capm/agile-frameworks-methodologies-and-methodologies-for-capm-certification/5-determine-how-to-prepare-and-execute-agile-task-management-steps/
#AgileProjectManagement #TaskPrioritization #CAPM
KnowledgeMap
CAPM Agile Task Management
Learn Agile Task Management for CAPM Certification, including task prioritization, success criteria, and key study resources.
👍1🔥1
#CAPM Question #4293
What is one benefit of documenting the change control process?
What is one benefit of documenting the change control process?
Anonymous Quiz
17%
a. Stakeholders understand the difficulty of managing requirements.
54%
b. Stakeholders know how to request changes.
13%
c. Stakeholders have a schedule of changes to be deployed.
15%
d. Stakeholders are shielded from how changes are assessed.
👍1
#CAPM Question #811
The common control limits for quality are:
The common control limits for quality are:
Anonymous Quiz
31%
a. 2 standard deviations
20%
b. 4 standard deviations
33%
c. 3 standard deviations
16%
d. 6 standard deviations
🤔3
What are the key artifacts commonly used in adaptive projects to document project controls, and how can they be applied effectively in Agile environments?
Referer to:https://knowledgemap.pm/certifications/capm/agile-frameworks-methodologies-and-methodologies-for-capm-certification/3-determine-how-to-document-project-controls-for-an-adaptive-project/
#ProjectControls #AgileMethodology #CAPM
Referer to:https://knowledgemap.pm/certifications/capm/agile-frameworks-methodologies-and-methodologies-for-capm-certification/3-determine-how-to-document-project-controls-for-an-adaptive-project/
#ProjectControls #AgileMethodology #CAPM
KnowledgeMap
CAPM Adaptive Project Controls
Learn how to document adaptive project controls in Agile to effectively manage and monitor project progress.
👍2
#CAPM Question #802
Which of the following is NOT a goal for members involved in team development?
Which of the following is NOT a goal for members involved in team development?
Anonymous Quiz
11%
a. They must have a reason for working together.
11%
b. They must be committed to working together.
31%
c. They must be independent.
47%
d. They must have a moderate level of competition and conflict.
👍1
What are the key steps and resources involved in validating project requirements through product delivery, as outlined in the CAPM certification materials?
Referer to:https://knowledgemap.pm/certifications/capm/business-analysis-frameworks/6-validate-requirements-through-product-delivery/
#CAPM #RequirementsValidation #ProductDelivery
Referer to:https://knowledgemap.pm/certifications/capm/business-analysis-frameworks/6-validate-requirements-through-product-delivery/
#CAPM #RequirementsValidation #ProductDelivery
KnowledgeMap
CAPM Requirements Validation Product Delivery
Learn CAPM Requirements Validation Product Delivery. Master acceptance criteria and ensure product readiness for successful project outcomes.
👍1
#CAPM Question #3498
Which of the following are not inputs for the validate scope process?
Answers:
a. The project management plan which containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
b. The validated deliverables, completed and checked for correctness by the perform quality control process.
c. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.
d. The RACI matrix, describing accountabilities for scope validation and acceptance.
Which of the following are not inputs for the validate scope process?
Answers:
a. The project management plan which containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
b. The validated deliverables, completed and checked for correctness by the perform quality control process.
c. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.
d. The RACI matrix, describing accountabilities for scope validation and acceptance.
How long does it take to process a CAPM certification application?
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/application-review/
#CAPM #PMI #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/capm/certification-process/application-review/
#CAPM #PMI #ProjectManagement
KnowledgeMap
CAPM Application Review
The application review for the CAPM certification takes 24 hours unless selected for an audit. Share your experience with the review process!
👍2