#CAPM Question #3784
When controlling a schedule what data analysis technique would NOT be used?
Anonymous Quiz
31%
a. Performance reviews.
22%
b. Iteration burndown charts.
18%
c. Earned value analysis.
29%
d. Schedule change control
👏1
#CAPM Question #1876
The Scrum Master and the Product Owner disagree on the value of a Product Backlog item. In order to resolve the disagreement, the first step the Scrum Master should take is to ask:
Anonymous Quiz
80%
a. The Product Owner to clarify the requirement.
5%
b. The business owner to resolve the problem.
16%
c. The business analyst to research the product value.
0%
d. Another project manager how to resolve the problem.
#CAPM Question #3498
Which of the following are not inputs for the validate scope process?
Answers:
a. The project management plan which containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.
b. The validated deliverables, completed and checked for correctness by the perform quality control process.
c. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.
d. The RACI matrix, describing accountabilities for scope validation and acceptance.