#PgMP Question #4407
You are working on a program to build the largest resort hotel in your country. The resort will feature cutting-edge wireless technology, smart TVs, pools for all age groups, three beaches, and 11 restaurants. While the area is known for its beaches, the local competition has fallen behind in adopting modern technologies, causing existing resorts to lose long-time customers. You believe that a key benefit of your program will be to attract tourists back to the area and boost the local economy.
A competitive Request for Proposal (RFP) process was conducted for the architectural work, resulting in seven bids. You selected a well-respected contractor for the job. A member of your team has been assigned to oversee the contractorโ€™s work. This team member should ensure:
Answers:
a. There are no unresolved contractual issues.
b. There is a designated space in the knowledge repository for the contractor to post status updates.
c. That weekly meetings are scheduled with contractor representatives to review progress, issues, and risks.
d. That an architectural engineer is assigned to support the component manager throughout the work.