COPs preparation plan
For the valve numbers see the picture below.
In this plan following sequences will be described:
- Preparation of cargo lines and line up;
- Priming and preparation of cargo pumps;
- Start of cargo pumps;
- Start of discharging.
It is assumed that the grade of the cargo is the same for each cargo line, no segregation.
Also three empty cargo arms without any back pressure are connected to
ship's manifolds.
Sequence for deck and pumproom:
1. Open tank suction valves
- Open COT-1 P/S main suction CS-132, 133;
- Open COT-2 P/S main suction CS-136, 137;
- Open COT-3 P/S main suction CS-142, 143;
2. Open bulkhead master valves in pumproom
- Open for Line-1: CO-201;
- Open for Line-2: CO-202;
- Open for Line-3: CO-203;
3. Open pumps suction valves
- Open for COP-1: CO-220;
- Open for COP-2: CO-221;
- Open for COP-3: CO-222;
4. Discharge valves closed for all pumps (check)
- Close for COP-1: CO-204;
- Close for COP-2: CO-205;
- Close for COP-3: CO-206;
5. Open vent valve between gas separator and pump casing
- Do this for all three pumps;
6. Open AUS gas extraction valves
- Open for COS-1;
- Open for COS-2;
- Open for COS-3;
7. Once suction gauge shows positive and all separators fills, the GEVs can be shut
- Close for COS-1;
- Close for COS-2;
- Close for COS-3;
8. Open AUS pneumatic discharge valves
- Open for COP-1;
- Open for COP-2;
- Open for COP-3;
9. Start pumps at slow RPM for abt 10 min for warming-up
- Ensure that no any abnormal condition;
10. Increase pump RPM up to abt 600 with control from ECR
11. Take control of the pumps from ECR to CCR
12. Open manifolds
- Line-1: CO-302;
- Line-2: CO-304;
- Line-3: CO-306;
13. When discharge pressure risen, gradually and equivalently open discharge valve on each pump
- For COP-1: CO-204;
- For COP-2: CO-205;
- For COP-3: CO-206;
14. When pressure stabilized and ensured that there are no any vibrations,
strange noises and/or leakages, then increase pumps RPM.
Remarks:
AUS - Automatic Unloading System
GEV - Gas Extraction Valve
COP - Cargo Oil Pump
COS - Cargo Oil Separator
COT - Cargo Oil Tank
For the valve numbers see the picture below.
In this plan following sequences will be described:
- Preparation of cargo lines and line up;
- Priming and preparation of cargo pumps;
- Start of cargo pumps;
- Start of discharging.
It is assumed that the grade of the cargo is the same for each cargo line, no segregation.
Also three empty cargo arms without any back pressure are connected to
ship's manifolds.
Sequence for deck and pumproom:
1. Open tank suction valves
- Open COT-1 P/S main suction CS-132, 133;
- Open COT-2 P/S main suction CS-136, 137;
- Open COT-3 P/S main suction CS-142, 143;
2. Open bulkhead master valves in pumproom
- Open for Line-1: CO-201;
- Open for Line-2: CO-202;
- Open for Line-3: CO-203;
3. Open pumps suction valves
- Open for COP-1: CO-220;
- Open for COP-2: CO-221;
- Open for COP-3: CO-222;
4. Discharge valves closed for all pumps (check)
- Close for COP-1: CO-204;
- Close for COP-2: CO-205;
- Close for COP-3: CO-206;
5. Open vent valve between gas separator and pump casing
- Do this for all three pumps;
6. Open AUS gas extraction valves
- Open for COS-1;
- Open for COS-2;
- Open for COS-3;
7. Once suction gauge shows positive and all separators fills, the GEVs can be shut
- Close for COS-1;
- Close for COS-2;
- Close for COS-3;
8. Open AUS pneumatic discharge valves
- Open for COP-1;
- Open for COP-2;
- Open for COP-3;
9. Start pumps at slow RPM for abt 10 min for warming-up
- Ensure that no any abnormal condition;
10. Increase pump RPM up to abt 600 with control from ECR
11. Take control of the pumps from ECR to CCR
12. Open manifolds
- Line-1: CO-302;
- Line-2: CO-304;
- Line-3: CO-306;
13. When discharge pressure risen, gradually and equivalently open discharge valve on each pump
- For COP-1: CO-204;
- For COP-2: CO-205;
- For COP-3: CO-206;
14. When pressure stabilized and ensured that there are no any vibrations,
strange noises and/or leakages, then increase pumps RPM.
Remarks:
AUS - Automatic Unloading System
GEV - Gas Extraction Valve
COP - Cargo Oil Pump
COS - Cargo Oil Separator
COT - Cargo Oil Tank
👍3🔥1
Seagull answers: https://drive.google.com/open?id=1FgejPJpWTRW_IiaMkLJj_RtOPZ6hcQmI
Скачать одним файлом: https://drive.google.com/open?id=1-iZnif_1O_bGwDtPIPV7i0gNjqvwdbxW
Скачать одним файлом: https://drive.google.com/open?id=1-iZnif_1O_bGwDtPIPV7i0gNjqvwdbxW
sharlay_mppss.pdf
16 MB
Пожалуй лучшие МППСС с комментариями. Автор: Шарлай Георгий Николаевич, пособие 2017 года.
Скачать: https://drive.google.com/open?id=1QBnToLS69ZQMxhX57dXhz_K0LZTvy2hK
#colreg #мппсс #sharlay
Скачать: https://drive.google.com/open?id=1QBnToLS69ZQMxhX57dXhz_K0LZTvy2hK
#colreg #мппсс #sharlay
🔥1
✅ Добавил на канал возможность обсуждения. Заходим в Messroom и общаемся в чате все вместе!
🔥2
👷🏿♂️Вот вам несколько фото обычного рабочего дня матроса. Чем старше судно, тем больше работ по покраске. Но прежде чем красить, нужно подготовить поверхность, удалить ржавчину и остальной шлак. Работа пыльная и громкая. Именно поэтому всем обязательно одевать защитные очки, наушники, перчатки и т.д.
🍳 В особо теплых регионах палуба раскаляется так, что на ней можно пожарить омлет. В таких условиях работать особо трудно. Делаем больше перерывов и берём много воды на рабочие места.
⏩ Зачастую на протяжении всего трансокеанского перехода эти работы не прекращаются. Объем очень большой, а людей ограниченное количество.
🍳 В особо теплых регионах палуба раскаляется так, что на ней можно пожарить омлет. В таких условиях работать особо трудно. Делаем больше перерывов и берём много воды на рабочие места.
⏩ Зачастую на протяжении всего трансокеанского перехода эти работы не прекращаются. Объем очень большой, а людей ограниченное количество.
🔥1