Project of Protecting El-Gameel Embouchure – Port said City owned by The shore protection public Egyptian authority , it contains
Construction of two groins, each with a length of 350
meters, at the boundaries of the estuary. The project involves several key components, including the supply and installation of geotextile mats and a gradient weights of dolomite stones have been supplied and installed.
The project have also entailed the casting, curing, and installation of tetrapod blocks, each weighing 2 tons.
#constructionequipment #construction #project
Construction of two groins, each with a length of 350
meters, at the boundaries of the estuary. The project involves several key components, including the supply and installation of geotextile mats and a gradient weights of dolomite stones have been supplied and installed.
The project have also entailed the casting, curing, and installation of tetrapod blocks, each weighing 2 tons.
#constructionequipment #construction #project
❤1
The extension of berth 98 at the El-Dekheila port quay wall by 50 meters with the construction of two mooring dolphins with dimensions 10*8*2 m. Through Installation of 18 steel pipe piles filled with reinforced concrete, as well as the connection of the mooring dolphins via catwalks measuring 40 meters in length. #construction #concrete
❤1
Project of Protection of low-lying coastal areas west Nile River Estuary Rashid Branch – New Rashid City – El Behira owned by The shore protection public Egyptian authority , it contains
Construction of sand bridge to protect low-lying area from immersion at 200 m from shoreline with sections that consists of dolomite stone revetment, cement mixture and crushed stone layer with a base of geotextile mats and finally putting sand traps to build the area.
#construction #project
Construction of sand bridge to protect low-lying area from immersion at 200 m from shoreline with sections that consists of dolomite stone revetment, cement mixture and crushed stone layer with a base of geotextile mats and finally putting sand traps to build the area.
#construction #project
❤1
Project of Residences Buildings at El-Andalos Region New Cairo City, it contains
Construction of 20,000 M2 of apartment building owned by the new urban communities Authority for the project of medium housing (DAR MISR PROJECT) at El-Andalos region new Cairo city.
#construction #building #project #housing
Construction of 20,000 M2 of apartment building owned by the new urban communities Authority for the project of medium housing (DAR MISR PROJECT) at El-Andalos region new Cairo city.
#construction #building #project #housing
❤1
Project of Resident Buildings at the Western of EL Sherooq, it contains
Construction of 60,000 m2 of apartment building owned by the new urban communities Authority for the project of medium housing (DAR MISR PROJECT) at El Sherooq
#construction #building #project #housing
Construction of 60,000 m2 of apartment building owned by the new urban communities Authority for the project of medium housing (DAR MISR PROJECT) at El Sherooq
#construction #building #project #housing
❤1
Project of Construction of Marine Berth at Borolos Harbor, it contains
Construction of marine quay of 150 meters in length for the installation of heavy equipment for Borolos Power Plant, including 6000 square meters reinforced concrete back yard, storage yard with concrete flooring tiles expands 12000 square meters and 2 kilometers concrete roads.
#construction #project #concrete #power #marine
Construction of marine quay of 150 meters in length for the installation of heavy equipment for Borolos Power Plant, including 6000 square meters reinforced concrete back yard, storage yard with concrete flooring tiles expands 12000 square meters and 2 kilometers concrete roads.
#construction #project #concrete #power #marine
❤1
Project of Construction of Y Groins for The Region Eastern Damietta Port and it contains,
Constructing a 300m seawall of gradient weights dolomite stones and Y shaped groins of a 250m length for the body and 100m for each wing. Along with executing sand nourishment for 1200 m of the shore line and another seawall 700m in length to protect existing road. Finally & for the first time in Egypt, constructing 100 m for the shore protection by using the Geotube as a trail project.
#construction #egypt #project
Constructing a 300m seawall of gradient weights dolomite stones and Y shaped groins of a 250m length for the body and 100m for each wing. Along with executing sand nourishment for 1200 m of the shore line and another seawall 700m in length to protect existing road. Finally & for the first time in Egypt, constructing 100 m for the shore protection by using the Geotube as a trail project.