Daily Question #3106
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
Answers:
a. Schedule a training course for the new team member to fill in their gaps in experience.
b. Log this as an issue in the project issue log and speak with the resource manager.
c. Provide weekly feedback to all project team members, including the new member.
d. Ensure that coaching meetings are in place for this team member within the project timeline.
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
Answers:
a. Schedule a training course for the new team member to fill in their gaps in experience.
b. Log this as an issue in the project issue log and speak with the resource manager.
c. Provide weekly feedback to all project team members, including the new member.
d. Ensure that coaching meetings are in place for this team member within the project timeline.
๐3๐ค1
Daily Question #719
All of the following would occur during the Close Project or Phase process EXCEPT:
All of the following would occur during the Close Project or Phase process EXCEPT:
Anonymous Quiz
3%
a. Creating lessons learned
13%
b. Formal acceptance
40%
c. Reducing resource spending
44%
d. Performing cost-benefit analysis
Daily Question #3881
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders.
What should the project manager do to improve project performance?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders.
What should the project manager do to improve project performance?
Anonymous Quiz
13%
a. Ask stakeholders to communicate with the project manager and not directly with the team.
31%
b. Empower the team members to remove obstacles and blockers.
41%
c. Address and remove obstacles and blockers for the team.
15%
d. Add blockers to the issue log and risk management plan.
๐ค1
Daily Question #22
At what point in the project would stakeholders have the most ability to influence the final outputs of the project product?
At what point in the project would stakeholders have the most ability to influence the final outputs of the project product?
Anonymous Quiz
21%
a. Carrying out the work
36%
b. Organizing and preparing
36%
c. Starting the project
7%
d. Closing the project
๐3๐ค1
Daily Question #4091
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
Answers:
a. Inform the stakeholder that the new requirement will be considered in the next release planning session.
b. Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.
c. Ask the product owner to determine if this requirement needs to be treated as a top priority.
d. Direct the development team to work on this requirement right away.
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
Answers:
a. Inform the stakeholder that the new requirement will be considered in the next release planning session.
b. Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.
c. Ask the product owner to determine if this requirement needs to be treated as a top priority.
d. Direct the development team to work on this requirement right away.
๐1
๐ค1
Daily Question #1702
A high-performance Agile team:
Answers:
a. is fully committed to team success yet respects the prescribed roles and titles of team members.
b. owns its decisions and commitments and is motivated to succeed at any cost.
c. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
d. produces a high volume of business value through intensive collaboration and avoidance of conflict.
A high-performance Agile team:
Answers:
a. is fully committed to team success yet respects the prescribed roles and titles of team members.
b. owns its decisions and commitments and is motivated to succeed at any cost.
c. is self-organizing, empowered to make decisions, and consensus-driven, with constructive disagreement.
d. produces a high volume of business value through intensive collaboration and avoidance of conflict.
๐1
Daily Question #5392
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service.
What should the project manager do next?
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service.
What should the project manager do next?
๐1
Daily Question #4995
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
๐2
The First Step in Your Certification Journey! ๐
On February 10, a new CAPM certification preparation cycle begins! ๐ฏ Program Details:
- Cost: $420*
- Duration: 2 months
- Certificate for 23 training hours
- Full Access to the KnowledgeMap platform
- Language: Ukrainian
- Mentor: @s_martynenko
๐ Open Onboarding Session
๐ Date: February 10
โฐ Time: 6:00 PM (GMT+2:00)
๐ Join here: Google Calendar Event
๐ก Still deciding whether to start with CAPM or aim directly for PMP?
Join the free onboarding session! @s_martynenko and @AnatoliiSavin will share valuable insights, explain the certification process, and answer all your questions.
๐ฉ Have Questions?
Message @AnatoliiSavin or @s_martynenko โ weโre happy to help!
Or join the CAPM Telegram Group: Join Now
*๐ฐ Savings Options:
1. Free Training: Available for veterans and military personnel.
2. Early Bird Discount: Pay in full by February 10 and get 50% off!
3. Flexible Payments: Split the payment into two installments for easier budgeting.
4. Self-Study Option: Purchase access to KnowledgeMap and study independently. All materials are included, with pricing ranging from $10 to $50 (depending on the training duration).
Letโs take this step together toward your CAPM certification and career growth! ๐
๐ Upcoming Certification Prep Groups:
๐น PMP Prep โ Starts February 24
๐น PMI-RMP Prep โ Starts March 10
๐น All Marathon'25 Certifications โ Learn More
On February 10, a new CAPM certification preparation cycle begins! ๐ฏ Program Details:
- Cost: $420*
- Duration: 2 months
- Certificate for 23 training hours
- Full Access to the KnowledgeMap platform
- Language: Ukrainian
- Mentor: @s_martynenko
๐ Open Onboarding Session
๐ Date: February 10
โฐ Time: 6:00 PM (GMT+2:00)
๐ Join here: Google Calendar Event
๐ก Still deciding whether to start with CAPM or aim directly for PMP?
Join the free onboarding session! @s_martynenko and @AnatoliiSavin will share valuable insights, explain the certification process, and answer all your questions.
๐ฉ Have Questions?
Message @AnatoliiSavin or @s_martynenko โ weโre happy to help!
Or join the CAPM Telegram Group: Join Now
*๐ฐ Savings Options:
1. Free Training: Available for veterans and military personnel.
2. Early Bird Discount: Pay in full by February 10 and get 50% off!
3. Flexible Payments: Split the payment into two installments for easier budgeting.
4. Self-Study Option: Purchase access to KnowledgeMap and study independently. All materials are included, with pricing ranging from $10 to $50 (depending on the training duration).
Letโs take this step together toward your CAPM certification and career growth! ๐
๐ Upcoming Certification Prep Groups:
๐น PMP Prep โ Starts February 24
๐น PMI-RMP Prep โ Starts March 10
๐น All Marathon'25 Certifications โ Learn More
๐ฅ1
Daily Question #5236
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
๐1
Daily Question #5383
A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted. However, a government agency has recently introduced new standards that may significantly impact the project. The deliverables must be changed to align with the new quality standards.
What should the project manager do?
Answers:
a. Set up a structured, independent processes to determine if project activities followed the standards.
b. Schedule training for the project team on the new regulations introduced by the government agency.
c. Evaluate the impact the new regulations will have on the project and submit a change request.
d. Update the lessons learned register and inform senior management of the new standards.
A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted. However, a government agency has recently introduced new standards that may significantly impact the project. The deliverables must be changed to align with the new quality standards.
What should the project manager do?
Answers:
a. Set up a structured, independent processes to determine if project activities followed the standards.
b. Schedule training for the project team on the new regulations introduced by the government agency.
c. Evaluate the impact the new regulations will have on the project and submit a change request.
d. Update the lessons learned register and inform senior management of the new standards.
๐1
Daily Question #4326
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
Answers #4326
Anonymous Quiz
41%
a. MoSCoW.
20%
b. Requirements traceability.
28%
c. Feasibility analysis.
11%
d. Interface analysis.
๐2