Daily Question #4925
During an agile project, a project manager lost one of the resources and, at the same time, uncovered new requirements, which were added to the backlog.
What should the project manager do next?
Answers:
a. Reevaluate the project schedule as the velocity will be impacted by the loss of resources.
b. Reevaluate the backlog priority with the product owner since the velocity has been impacted.
c. Reevaluate the scope of the current iteration to keep the same velocity and timeline.
d. Reevaluate the velocity as the iteration duration will be impacted by new requirements.
Answers #4925
Anonymous Quiz
21%
a
48%
b
17%
c
14%
d
👍1
Daily Question #5049
A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.
What should the project manager do to address this concern?
Daily Question #1738
You have recently been named as the manager of a new project under contract. The sponsor of the project gave you the contract signed by the customer and a statement of work. He asked you to go on with initiation.
Which document should you develop next?
Daily Question #5203
A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.
What should the project manager do to address this issue?
Daily Question #21
At what stage in the project life cycle would costs be the lowest?
Anonymous Quiz
37%
a. Starting the Project
29%
b. Organizing and Preparing
2%
c. Carrying Out the Work
32%
d. Ending the Project
👍4
Daily Question #6910
A project manager has introduced the Obeya/Big Room approach to a complex construction project to improve communication and decision-making among cross-functional teams. While the approach initially helped streamline collaboration, the project manager starts noticing that meetings are becoming unproductive, with team members spending more time in the Big Room without making meaningful progress on their tasks. Some stakeholders also feel disengaged because their input is overlooked.

What should the project manager recognize as a common pitfall of using the Obeya/Big Room, and how can it be addressed?
Answers:
a. Using the Big Room only for high-level decision-making, which slows down project execution.
b. Allowing only a small group of people to attend the Big Room sessions, excluding key team members from the decision-making process.
c. Scheduling Big Room sessions too infrequently, which leads to delayed decision-making and lack of real-time collaboration.
d. Failing to establish a clear structure and agenda, leading to unproductive meetings and disengagement among team members.
Answers #6910
Anonymous Quiz
22%
a
8%
b
10%
c
61%
d
👍1
Daily Question #5025
During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project timeline.
How should the project manager address the situation?
Answers:
a. Discuss the vacation plan and include scheduling changes in the change log database.
b. Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.
c. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.
d. Push out the project timeline according to the vacation plan in place based on the recent company policy.
Answers #5025
Anonymous Quiz
26%
a
9%
b
53%
c
12%
d
🤔1
Daily Question #1956
Assume you work for a technology company that is publically owned, and the value of its stock is tracked daily by the CFO and is reported to the portfolio manager. Quarterly meetings are held with stockholders as the company went public through an Initial public offering (IPO) last year. These stockholders:
Daily Question #2995
A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team's work?
Answers:
a. Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.
b. Review the issue with the project sponsor and work to reduce the scope for that team.
c. Guide all team members and bring in external consultants to complete the work.
d. Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.
Answers #2995
Anonymous Quiz
84%
a
3%
b
3%
c
9%
d
👍1
Daily Question #4757
A project team member wants to select specific challenging tasks in the subsequent iteration.
How can the project lead help the team member in the next iteration?
Anonymous Quiz
9%
a. Assign the challenging tasks to the team member.
14%
b. Ask the product owner to assign the challenging tasks.
19%
c. Reprioritize the challenging tasks to future sprints.
58%
d. Coach the team member to pick up the challenging tasks.
2