Daily Question #5092
A project manager for a technology project is informed by the cybersecurity team that there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
Answers:
a. Update the scope management plan to track the new government requirements.
b. Accept the cybersecurity team's request as the security of the company is at risk of being noncompliant.
c. Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.
d. Request a change through the change control process to manage the new cybersecurity requirements.
A project manager for a technology project is informed by the cybersecurity team that there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
Answers:
a. Update the scope management plan to track the new government requirements.
b. Accept the cybersecurity team's request as the security of the company is at risk of being noncompliant.
c. Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.
d. Request a change through the change control process to manage the new cybersecurity requirements.
đ3
Daily Question #1337
You have been asked to build a monument to the King of Morovia. The monument must use materials that are native to the country.
In planning your resources, what might you need to consider?
You have been asked to build a monument to the King of Morovia. The monument must use materials that are native to the country.
In planning your resources, what might you need to consider?
Anonymous Quiz
33%
a. The skill of the locals to work with the resources.
25%
b. How much it will cost to mine the materials.
30%
c. The risks involved with working in a third-world country.
12%
d. The fluctuation of the local currency.
đ2
Daily Question #758
Confirming scope delivery is a practice of:
Confirming scope delivery is a practice of:
Anonymous Quiz
6%
a. Directing a project
16%
b. Initiating a project
42%
c. Controlling a project
36%
d. Managing delivery
đ¤2
Daily Question #5145
In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who have never attended project update meetings is complaining to the project sponsor that they know very little about the project.
What should the project manager do?
Answers:
a. Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.
b. Ensure that the stakeholders who are complaining are present for the next project update meetings.
c. Record the regular project update meeting and share it with all stakeholders after the meeting is completed.
d. Change the meeting time to the working time zones of the stakeholders who are complaining.
In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who have never attended project update meetings is complaining to the project sponsor that they know very little about the project.
What should the project manager do?
Answers:
a. Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.
b. Ensure that the stakeholders who are complaining are present for the next project update meetings.
c. Record the regular project update meeting and share it with all stakeholders after the meeting is completed.
d. Change the meeting time to the working time zones of the stakeholders who are complaining.
đ1
Daily Question #5110
A project manager is implementing an enterprise-wide software project. The project has a great business impact and is fully supported by senior management. However, the project manager is facing difficulties getting the support of several key departments.
What should the project manager do?
A project manager is implementing an enterprise-wide software project. The project has a great business impact and is fully supported by senior management. However, the project manager is facing difficulties getting the support of several key departments.
What should the project manager do?
đ1
Daily Question #1061
The technique that assists in identifying which variables have the most influence on the overall outcome is called:
The technique that assists in identifying which variables have the most influence on the overall outcome is called:
Anonymous Quiz
42%
a. Cause-and-effect diagrams
10%
b. Benchmarking
20%
c. Design of Experiments
28%
d. Fishbone Diagrams
đ¤4
Daily Question #3346
Which of the four Portfolio Strategic Management processes involves an output of high-level portfolio planning that graphically depicts all portfolio elements need to achieve organizational strategy and objectives?
Which of the four Portfolio Strategic Management processes involves an output of high-level portfolio planning that graphically depicts all portfolio elements need to achieve organizational strategy and objectives?
Daily Question #118
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
đ1
Daily Question #2700
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
Answers:
a. Plan Risk Responses, to outline the possible options to bypass the system performance issue.
b. Perform Qualitative Risk Analysis, to assess the extent of the system performance impact.
c. Monitor Risks, to install system performance monitoring tools and update the risk register.
d. Perform Quantitative Risk Analysis, to outline the details of the system performance issues.
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
Answers:
a. Plan Risk Responses, to outline the possible options to bypass the system performance issue.
b. Perform Qualitative Risk Analysis, to assess the extent of the system performance impact.
c. Monitor Risks, to install system performance monitoring tools and update the risk register.
d. Perform Quantitative Risk Analysis, to outline the details of the system performance issues.
đ2đ¨1
Daily Question #2757
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception of the company's brand.
What should the project manager have done to prevent this?
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception of the company's brand.
What should the project manager have done to prevent this?
đ¤2
Training Starts Soon â You Still Have Time to Enroll!
PMP: Your key to global opportunities and career growth in a changing world!
Boost your credibility, master your leadership and earn more with PMP!
1. Military Support: Education is free for Ukrainian veterans and military personnel.
2. Flexible Payment Options: Pay in 2-3 installments for easier budgeting.
3. Early Birds: Pay in full by April, 7 for a 20% discount.
4. Self-Study: Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
5. For PMI Ukraine members: additional 10% discount.
đ Note:
All certifications of Marathon '25 - KnowledgeMap.pm/Marathon
#pmp #pmpcertification #pmpexam #pmpprep #projectmanagement #knowledgemap
Please open Telegram to view this post
VIEW IN TELEGRAM
đĨ2
What is the purpose of the CAPM Agile Methodologies Domain Mock Exam, and how can it help you prepare for the real CAPM exam?
Referer to:https://knowledgemap.pm/certifications/capm-certification/capm-exam-preparation-with-pmbok/take-capm-agile-methodologies-domain-mock-exam/
#CAPM #AgileFrameworks #MockExam
Referer to:https://knowledgemap.pm/certifications/capm-certification/capm-exam-preparation-with-pmbok/take-capm-agile-methodologies-domain-mock-exam/
#CAPM #AgileFrameworks #MockExam
KnowledgeMap
Agile Frameworks CAPM Mock Exam
Prepare for success with the Agile Frameworks CAPM Mock Exam. Test your knowledge and refresh your skills for the real exam.
đ1