𝗞𝗻𝗼𝘄𝗹𝗲𝗱𝗴𝗲𝗠𝗮𝗽
1.97K subscribers
98 photos
569 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#CAPM Question #3762
You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves five different sellers and 20 members of your company on the project team. You want to quickly review where the project now stands. Which of the following reports would be the MOST helpful in finding such information?
👍1
#PMP Question #5316
A project manager is leading the first agile project for the organization. During the kick-off meeting, the project manager notices that the team does not have the same understanding of agile approaches. The project manager is concerned about the impact of that confusion.
What should the project manager do to address this situation?
#PMP Question #2971
A subcontractor informs the project manager that they are unable to supply a key component to the project.
What should the project manager do?
Answers:
a. Discuss the issue with the project sponsor and request extra time and budget to obtain the component from a different supplier.
b. Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response.
c. Submit a change request to the change control board (CCB) for changes to the performance measurement baseline to obtain the component from a different supplier.
d. Raise a new issue in the issue log and convene subject matter experts (SMEs) and relevant stakeholders to identify alternatives to address the problem.
👍1
Answers #2971
Anonymous Quiz
9%
a
30%
b
22%
c
39%
d
👍1
#PMP Question #2981
A project manager receives a voicemail from a business analyst on the project team. The business analyst indicates that an internal stakeholder is upset that they were not included before the project began. The stakeholder is asking for an addition to the requirements traceability matrix.
What should the project manager do to improve the stakeholder relationship?
Answers:
a. Consult the project scope document to make sure the addition is in scope.
b. Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list.
c. Initiate a project change request so the change control board (CCB) can decide if it is in scope.
d. Engage the stakeholder to solicit more information before responding to the request.
👍1
Answers #2981
Anonymous Quiz
14%
a
45%
b
14%
c
27%
d
👍1
#CAPM Question #4919
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely. Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures.
What should the project manager do?
👍1
#PMP Question #123
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
Answers:
a. Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.
b. Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.
c. Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.
d. Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.
#PMP Question #3291
A high-tech borehole project was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six months after its completion it was determined that the villagers could not access water.
What caused this situation to occur?
👍1