#PMP Question #1729
You are planning quality management for your project.
How can a process flowchart help you?
Anonymous Quiz
19%
a. It may help identify outliers.
66%
b. It may help understand the COQ in a process.
13%
c. It may help spot accountable staff.
3%
d. It may help react later.
👍1
#PMP Question #1146
You are approximately 30% through your project and the sponsor wants a forecast of the final budget based on what has already been spent to determine if performance is improving or deteriorating.
You create an S-curve chart display of what kind of performance report:
👍1
#PMP Question #3396
A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery of products developed by all the teams. Some team members indicate they are on a very tight timeline and would attend the Monday meeting but not the daily standups.
What should the project manager do to ensure all team members participate in daily standup meetings?
Answers:
a. Analyze the team members' influence levels and schedule training on the importance of daily standups and their efficient nature.
b. Require all team members to attend the daily standups as they are requested by the project sponsor.
c. Inform the functional manager and replace some members who cannot join the daily standups.
d. Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.
👍1
Answers #3396
Anonymous Quiz
32%
a
14%
b
7%
c
46%
d
1👍1
#CAPM Question #898
The step that involves determining which risks might impact the project is:
Anonymous Quiz
38%
a. Risk identification.
13%
b. Risk planning.
44%
c. Risk analysis.
6%
d. Risk quantification.
🤔2
#PMP Question #145
A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
Answers:
a. Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver value incrementally.
b. Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the project.
c. Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end of the project.
d. Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.
👍1
Answers #145
Anonymous Quiz
24%
a
14%
b
24%
c
38%
d
👍1
#CAPM Question #3467
What is not the main purpose of a final project report?
Answers:
a. Preparing information on the acceptance of the final product, service, result or improvement.
b. Making stakeholders aware that the project has been closed out.
c. Acknowledging what has been done and achieved by all contributors.
d. If a project has been cancelled before completion and to explain the causes.
👍1
Answers #3467
Anonymous Quiz
38%
a
21%
b
13%
c
29%
d
🤔1
#PMP Question #2946
A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at risk.
What should the project manager do?