#PMP Question #1343
A member of the project management team has come up with a 3D model of stakeholder influence and interest in your project.
What could this be referred to?
Anonymous Quiz
28%
a. Stakeholder salience model.
13%
b. Stakeholder register.
25%
c. Stakeholder cube.
35%
d. Stakeholder engagement assessment matrix.
๐Ÿค”1
#PMP Question #5036
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards. In order to ensure this, what should the project manager define and document?
๐Ÿ‘1
#PMP Question #5253
During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a mini storage room. The sponsor insists on making this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
๐Ÿ‘1
#PMP Question #3527
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
Answers:
a. Meet with the project finance team to measure market variations and product impact.
b. Direct the project team to estimate user stories in greater detail.
c. Ask the product owner to prioritize the backlog items based on the return on investment (ROI).
d. Request that the project team develop a release plan and roadmap for the project.
๐Ÿ‘1
#PMP Question #4933
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
Answers:
a. Reviewed the communications management plan before inviting an external client representative to the meeting.
b. Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.
c. Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.
d. Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.
โค1๐Ÿ‘1
ะฏะบั– ั€ัƒัˆั–ั— ั‚ะฐ ะฝะฐะฒั‡ะฐะปัŒะฝั– ะผะฐั‚ะตั€ั–ะฐะปะธ ั” ะฝะตะพะฑั…ั–ะดะฝะธะผะธ ะดะปั ะพะฟะฐะฝัƒะฒะฐะฝะฝั ะทะฐะฒะดะฐะฝะฝั ยซะŸะปะฐะฝัƒะฒะฐะฝะฝั ั‚ะฐ ัƒะฟั€ะฐะฒะปั–ะฝะฝั ะพะฑััะณะพะผยป ะดะปั ัะตั€ั‚ะธั„ั–ะบะฐั†ั–ั— PMP?


Referer to:https://knowledgemap.pm/certifications/pmp/pmp-planning-focus-area-learning/2-2-develop-and-manage-project-scope/

#PMP #ProjectScope #PMBOK