#PMP Question #131
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholders, the product does not meet the quality standards required by regulations.
What should the project manager have done to avoid this?
Answers:
a. Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog.
b. Ensured that the project sponsor understood the scope of the project to avoid any future complaints.
c. Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration.
d. Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks.
๐Ÿ‘1
#PfMP Question #2379
The Portfolio Manager has worked with key stakeholders to establish and review a set of prioritization criteria for evaluating proposed and ongoing portfolio components. These criteria reflect organizational strategy, available resources, and component interdependencies.
What is the primary purpose of these criteria?
๐Ÿ‘1
#PMP Question #5097
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience. The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
๐Ÿ‘1
#CAPM Question #1436
Which is a strategic framework that is suitable for prompt lists?
Anonymous Quiz
38%
a. SCOPE.
38%
b. VUCA.
18%
c. FRESH.
5%
d. SOFTEN.
๐Ÿค”1
#PMP Question #1343
A member of the project management team has come up with a 3D model of stakeholder influence and interest in your project.
What could this be referred to?
Anonymous Quiz
28%
a. Stakeholder salience model.
13%
b. Stakeholder register.
25%
c. Stakeholder cube.
35%
d. Stakeholder engagement assessment matrix.
๐Ÿค”1
#PMP Question #5036
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards. In order to ensure this, what should the project manager define and document?
๐Ÿ‘1
#PMP Question #5253
During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a mini storage room. The sponsor insists on making this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
๐Ÿ‘1
#PMP Question #3527
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
Answers:
a. Meet with the project finance team to measure market variations and product impact.
b. Direct the project team to estimate user stories in greater detail.
c. Ask the product owner to prioritize the backlog items based on the return on investment (ROI).
d. Request that the project team develop a release plan and roadmap for the project.