#PMP Question #4737
A project manager is working with a team that is new to agile. One of the more influential stakeholders struggles with the nature of agile. The project manager knows that this stakeholder is needed as an advocate and wants to do everything possible to make the stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's performance?
๐Ÿ‘1
#PMP Question #3343
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
Answers:
a. Create a training schedule for the new team member to follow over the next few weeks.
b. Escalate the inquiry to the team member's functional manager.
c. Clarify the relevance of reviewing the documentation on the intranet.
d. Ask a senior team member to help the new team member navigate through all the documentation.
๐Ÿ‘1
#PfMP Question #1505
Values assist in guiding actions, evaluations, and decisions. Assume your organization is considering entering into a consortium to produce a helium-controlled car. Once the helium is supplied, additional amounts will not be needed. The car is to be personally appealing with a focus on an inexpensive cost to increase marketability. The consortium will enable each firm to capitalize on the expertise of the other firms in it, but the customer will view it as a separate entity. If your organization enters into the consortium, it must justify the value to the portfolio of doing so.
In addition, to ensure benefits are realized a focus is needed on:
๐Ÿค”2
#PMP Question #3391
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach. This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
๐Ÿ‘1
#PfMP Question #1967
A Portfolio Manager is reviewing the organizationโ€™s portfolio and working to identify all individuals and groups who may be affected by portfolio decisions. While considering executive leaders, component teams, and customers, additional stakeholder groups are also being evaluated.
Which stakeholder group is often overlooked during this process?
๐Ÿ‘2
#CAPM Question #1838
A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done.
What kind of leadership style should the project manager use at this stage?
Answers:
a. A directive style that makes decisions for the group to reach early outcomes.
b. A leadership style that coaches people who want help and fosters greater team collaboration.
c. A passive leadership style that allows the team to self-organize until the norming stage is reached.
d. A democratic style that uses techniques where majority opinion prevails.
๐Ÿ‘1