๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
1.97K subscribers
98 photos
570 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
ะฏะบั– ะบะปัŽั‡ะพะฒั– ั‡ะธะฝะฝะธะบะธ ั‚ะฐ ั€ะตะบะพะผะตะฝะดะพะฒะฐะฝั– ะฝะฐะฒั‡ะฐะปัŒะฝั– ะผะฐั‚ะตั€ั–ะฐะปะธ ะฝะตะพะฑั…ั–ะดะฝั– ะดะปั ะพะฟะฐะฝัƒะฒะฐะฝะฝั ะทะฐะฒะดะฐะฝะฝั ยซะกั‚ะฒะพั€ะตะฝะฝั ะบะพะผะฐะฝะดะธยป ะฒ ะผะตะถะฐั… ัะตั€ั‚ะธั„ั–ะบะฐั†ั–ั— PMP?

Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-6-build-a-team/

#PMP #TeamBuilding #ProjectManagement
๐Ÿ‘3โค1
#CAPM Question #2588
You work as a project manager. Your project is running late and you must respond to the risk. Which risk response can you choose that will also cause you to update the resource management plan?
Anonymous Quiz
7%
a. Team agreements
13%
b. Transference
42%
c. Crashing the project
38%
d. Fast tracking the project
๐Ÿ”ฅ1
#PMP Question #2680
A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module. The marketing department believes that the main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
Answers:
a. Traditional delivery, to ensure high quality and that the product meets market demands.
b. Extreme Programming (XP) delivery, to mitigate the high risk related to a new product.
c. Iterative delivery, to ensure that user feedback is incorporated into the second iteration.
d. Incremental delivery, to ensure that mobile capability is released fast to the users.
๐Ÿ‘1
#PMP Question #1719
What should not be your thoughts when you are organizing documents as lessons learned?
Answers:
a. Devise the lessons learned documentation in a wording that is easy to understand for a reader who is not familiar with the project.
b. Lessons learned must detail how certain groups or persons caused failures and delays, especially if they are inside the own organization.
c. Writing lessons learned should be an exercise enhancing your personal learning experience. Make sure you grasp what you are writing down.
d. Keep lessons learned documents in a place where they are easy to access and to retrieve for those who may later need the information.
๐Ÿ‘1
#PMP Question #4737
A project manager is working with a team that is new to agile. One of the more influential stakeholders struggles with the nature of agile. The project manager knows that this stakeholder is needed as an advocate and wants to do everything possible to make the stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's performance?
๐Ÿ‘1
#PMP Question #3343
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
Answers:
a. Create a training schedule for the new team member to follow over the next few weeks.
b. Escalate the inquiry to the team member's functional manager.
c. Clarify the relevance of reviewing the documentation on the intranet.
d. Ask a senior team member to help the new team member navigate through all the documentation.
๐Ÿ‘1
#PfMP Question #1505
Values assist in guiding actions, evaluations, and decisions. Assume your organization is considering entering into a consortium to produce a helium-controlled car. Once the helium is supplied, additional amounts will not be needed. The car is to be personally appealing with a focus on an inexpensive cost to increase marketability. The consortium will enable each firm to capitalize on the expertise of the other firms in it, but the customer will view it as a separate entity. If your organization enters into the consortium, it must justify the value to the portfolio of doing so.
In addition, to ensure benefits are realized a focus is needed on:
๐Ÿค”2