๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
1.97K subscribers
98 photos
570 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#PMP Question #663
The project is nearly complete. It has a schedule variance of $300 and a cost variance of -$900. All but one of the quality control inspections have been completed, and all inspections have met the quality requirements. All items in the issue log have been resolved, and many of the project resources have been released. The sponsor is about to call a meeting to obtain product verification when the customer notifies the project manager of a major requested change to the scope.
The project manager should:
๐Ÿ‘1
#PMP Question #3186
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time.
What should the project manager do?
Answers:
a. Record the issue then refocus the team's efforts on delivering the next set of deliverables.
b. Give the team member a formal warning for the negative impact due to failure to deliver and not meet deadlines.
c. Hold a team meeting to discuss team member commitments and communications.
d. Meet with the team member and work on a development plan for them to avoid missed deliverables in the future.
๐Ÿ˜2
#PMP Question #2976
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative.
How should the project manager qualify the project status?
๐Ÿ‘1
Where do you find the PMI-CPโ„ข Micro-Credential Exam, how long does it take, and what should you do to prepare your environment?

Referer to:https://knowledgemap.pm/certifications/pmi-cp/complete-course-modules/take-micro-credential-exam/

#PMICP #ProjectManagement #PMI
๐Ÿ‘1
#PMP Question #4924
A team member has a sudden emergency that may last for several days. There are no other team members who can cover his tasks and job duties.
What should the project manager do to address this concern?
โค1๐Ÿ‘1
#PMP Question #2381
In the middle of the execution phase for a big project, a new stakeholder who was unfamiliar with the project joined the board of directors and is in๏ฌ‚uencing the decisions made in the project. This change is impacting the project's progress.
What should the project manager do ๏ฌrst?
๐Ÿ‘1
#PMP Question #4833
At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other non-project-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
Answers:
a. Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.
b. Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.
c. Address this concern with the functional managers to ensure there will be no further delays.
d. Schedule a meeting with all of the functional managers to resolve the resource conflicts.
๐Ÿ‘1
#PMI-CP Question #5684
What does "contract performance monitoring" involve?
Answers:
a. Tracking and evaluating the contractor's performance against the contract terms and conditions
b. Negotiating new contract terms
c. Developing new contract proposals
d. Managing project budgets
๐Ÿ˜1