#PMP Question #1275
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
Answers:
a. Assign this member to facilitate the next meeting to ensure project team collaboration.
b. Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.
c. Review and update the project ground rules to establish clear expectations for meeting attendance.
d. Understand the reason for the team member's absence and encourage them to attend future meetings.
โค1๐Ÿ‘1
#PMP Question #5285
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared management asks the project manager to move forward with the project without an approved project scope statement.
What should the project manager do next?
Answers:
a. Escalate the issue to the project sponsor and add it to the risk register.
b. Refuse to work on the project because management is not following standard project management practices.
c. Meet with management to explain the potential problems with running a project without a project scope statement.
d. Start the project with inputs from the project charter to save time.
โค1๐Ÿ‘1
Don't use chatGPT to prepare for your exam.

Tested this today:

Real PMP question from Knowledge Map
ChatGPT โ†’ wrong
PMI Infinity โ†’ correct

Why?

ChatGPT = general internet knowledge
PMP = strict PMI standards

Mismatch = wrong answers

Donโ€™t prepare like this.
๐Ÿ‘3
#PMP Question #5254
A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase.
To ensure consistency for this hybrid delivery, what should the project manager do?
๐Ÿ‘1
#PMP Question #5142
A project manager finds an unexpected issue halfway through a customer's project. After analysis, the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
Answers:
a. Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline.
b. Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change.
c. Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline.
d. Absorb the additional cost for the additional resources internally so that the project completes within the timeline.
๐Ÿ‘1
#PMP Question #660
A new project manager is being mentored by a more experienced certified project management professional (PMP). The new project manager is having difficulty finding enough time to manage the project because the product and project scope are being progressively elaborated. The PMP-certified project manager mentions that the basic tools for project management, such as a work breakdown structure, can be used during project execution to assist the project manager.
For which of the following can a work breakdown structure be used?
๐Ÿค”2
#CAPM Question #4094
A PO (Product Owner) is essentially the same thing as a traditional PM (Project Manager).
Anonymous Quiz
7%
a. TRUE
93%
b. FALSE
๐Ÿฅด2
#CAPM Question #1279
The following chart lists stories for a release of an Agile project. If the velocity of the team is 10, how many iterations will be needed to complete all of the stories?
Anonymous Quiz
31%
a. 3
52%
b. 4
15%
c. 5
2%
d. 7