๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
1.97K subscribers
98 photos
578 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#PMP Question #5081
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams. The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
Answers:
a. Arrange a meeting with the managers and try to reach an agreement.
b. Communicate with the project sponsor regarding the need to resolve the conflict between the managers.
c. Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan.
d. Meet with both teams and their managers and try to figure out the root cause of the conflict.
๐Ÿ‘2
#CAPM Question #791
The amount of variation allowed in the budget before it requires consideration for re-baselining is likely to be found in which document?
Anonymous Quiz
19%
a. Cost baseline
10%
b. Overall Change Control Plan
19%
c. Cost Change Control System
52%
d. Cost Management Plan
๐Ÿ‘1
#PMP Question #1300
Which equation demonstrates the schedule performance index of a project?
Anonymous Quiz
7%
a. EV-AC
17%
b. EV/AC
20%
c. EV-PV
57%
d. EV/PV
#PMP Question #2649
A project team is executing a megaproject, and several contract requirements have been identi๏ฌed. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's ๏ฌnish date. However, during project execution, it was determined that the contract was required immediately.
What should the project manager do?
๐Ÿ‘1
#PMP Question #2937
A new project manager is assigned to lead an agile project. The project manager wants to use motivation to encourage the team to perform well throughout the project.
What should the project manager do?
๐Ÿค”1
PMI ะทะผั–ะฝัŽั” ะฟั€ะฐะฒะธะปะฐ: ะท 4-ะณะพ ะบะฒะฐั€ั‚ะฐะปัƒ 2026 ั€ะพะบัƒ 35 ะณะพะดะธะฝ ะฝะฐะฒั‡ะฐะฝะฝั ะฝะฐ ะบัƒั€ัะฐั… ะฟั–ะดะณะพั‚ะพะฒะบะธ ะดะพ PMP ะทะฐั€ะฐั…ะพะฒัƒะฒะฐั‚ะธะผัƒั‚ัŒัั ะปะธัˆะต ะฒั–ะด ATP ะฐะฑะพ ะฐะบั€ะตะดะธั‚ะพะฒะฐะฝะธั… ะฐะบะฐะดะตะผั–ั‡ะฝะธั… ะฟั€ะพะณั€ะฐะผ.
ะขะพะผัƒ ัะฐะผะต ะทะฐั€ะฐะท ั‡ะฐั ะฟั€ะธั”ะดะฝะฐั‚ะธัั ะดะพ KnowledgeMapโ„ข Mentor-to-Mentor โ€” ะบัƒั€ััƒ ะดะปั ะผะตะฝั‚ะพั€ั–ะฒ, ัะบั– ั…ะพั‡ัƒั‚ัŒ ัะธัั‚ะตะผะฝะพ ะณะพั‚ัƒะฒะฐั‚ะธ ะดะพ PMP ั‚ะฐ ั–ะฝัˆะธั… ะฟั€ะพั„ะตัั–ะนะฝะธั… ัะตั€ั‚ะธั„ั–ะบะฐั†ั–ะน, ะฐ ั‚ะฐะบะพะถ ะฟั€ะฐั†ัŽะฒะฐั‚ะธ ะท ััƒั‡ะฐัะฝะพัŽ ะฟะปะฐั‚ั„ะพั€ะผะพัŽ KnowledgeMap.

ะŸั€ะพ ะบัƒั€ั:
- ะ’ะฐั€ั‚ั–ัั‚ัŒ: โ‚ฌ900*
- ะขั€ะธะฒะฐะปั–ัั‚ัŒ: 9 ั‚ะธะถะฝั–ะฒ / 18 ะณะพะดะธะฝ
- 12 ะผั–ััั†ั–ะฒ ะดะพัั‚ัƒะฟัƒ ะดะพ KnowledgeMap ะดะปั ะฒัั–ั… ัƒั‡ะฝั–ะฒ ะผะตะฝั‚ะพั€ะฐ
- ะ”ะปั ั‚ะธั…, ั…ั‚ะพ ัƒัะฟั–ัˆะฝะพ ะฒะธะบะพะฝะฐั” ะฒัั– ะฒะฟั€ะฐะฒะธ โ€” ะผะพะถะปะธะฒั–ัั‚ัŒ ะพั‚ั€ะธะผะฐั‚ะธ ัั‚ะฐั‚ัƒั PMI Instructor ะฟั–ะด โ€œะฟะฐั€ะฐัะพะปัŒะบะพัŽโ€ KnowledgeMapโ„ข
- ะกั‚ะฐั€ั‚: 26 ะฑะตั€ะตะทะฝั ะพ 17:00
- ะ—ะฐะฝัั‚ั‚ั: ั‰ะพั‡ะตั‚ะฒะตั€ะณะฐ, 17:00โ€“19:00

ะ”ะพะดะฐะนั‚ะต ัะพะฑั– ะฒ ะบะฐะปะตะฝะดะฐั€: calendar.app.google/dtyVgAGzJKAzc41H7
TG-ั‡ะฐั‚: t.me/+MREXhxsWMoQ3MmVi

*ะฏะบ ะทะตะบะพะฝะพะผะธั‚ะธ:
- ะฑะตะทะบะพัˆั‚ะพะฒะฝะพ ะดะปั ะฒะตั‚ะตั€ะฐะฝั–ะฒ ั‚ะฐ ะฒั–ะนััŒะบะพะฒะพัะปัƒะถะฑะพะฒั†ั–ะฒ
- ะพะฟะปะฐั‚ะฐ ัƒ 2โ€“3 ะฟะปะฐั‚ะตะถั–
- ะทะฝะธะถะบะฐ 10% ะฟั€ะธ ะฟะพะฒะฝั–ะน ะพะฟะปะฐั‚ั– ะดะพ 26 ะฑะตั€ะตะทะฝั
- ะทะฝะธะถะบะฐ 5% ะดะปั ั‡ะปะตะฝั–ะฒ PMI Ukraine
ะžะฟะปะฐั‚ะฐ ะบัƒั€ััƒ Train the Trainer for PMI Authorized Exam Prep ะฝะต ะฒั…ะพะดะธั‚ัŒ ัƒ ะฒะฐั€ั‚ั–ัั‚ัŒ ะบัƒั€ััƒ KnowledgeMapโ„ข Mentor-to-Mentor.

ะ”ะตั‚ะฐะปัŒะฝะธะน ะพะฟะธั ะฟั€ะพะณั€ะฐะผะธ ะบัƒั€ััƒ: knowledgemap.pm/ua/mentor-to-mentor-course
๐Ÿ‘1