#PMP Question #5081
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams. The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
Answers:
a. Arrange a meeting with the managers and try to reach an agreement.
b. Communicate with the project sponsor regarding the need to resolve the conflict between the managers.
c. Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan.
d. Meet with both teams and their managers and try to figure out the root cause of the conflict.
๐Ÿ‘2
#CAPM Question #791
The amount of variation allowed in the budget before it requires consideration for re-baselining is likely to be found in which document?
Anonymous Quiz
19%
a. Cost baseline
10%
b. Overall Change Control Plan
19%
c. Cost Change Control System
52%
d. Cost Management Plan
๐Ÿ‘1
#PMP Question #1300
Which equation demonstrates the schedule performance index of a project?
Anonymous Quiz
7%
a. EV-AC
17%
b. EV/AC
20%
c. EV-PV
57%
d. EV/PV
#PMP Question #2649
A project team is executing a megaproject, and several contract requirements have been identi๏ฌed. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's ๏ฌnish date. However, during project execution, it was determined that the contract was required immediately.
What should the project manager do?
๐Ÿ‘1