𝗞𝗻𝗼𝘄𝗹𝗲𝗱𝗴𝗲𝗠𝗮𝗽
1.97K subscribers
99 photos
581 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#PMP Question #5014
A key stakeholder has recently started to work in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder have only been exposed to predictive project approaches.
What should the project manager do?
Answers:
a. Inform the stakeholder that they must level their knowledge with other stakeholders.
b. Update the risk register with the potential impact and apprise the steering committee.
c. Inform the project management office (PMO) that the team will use a predictive approach for this project.
d. Allocate time to mentor the stakeholder in the selected project approach.
👍1
Answers #5014
Anonymous Quiz
7%
a
13%
b
9%
c
71%
d
👍1
#PMP Question #914
There are many variables that impact the accuracy of qualitative risk analysis.
Which of the following is NOT one of those variables:
Anonymous Quiz
14%
a. The stage in the project life cycle.
20%
b. The sensitivity of the project to the risk.
59%
c. The details of project stakeholders.
6%
d. The accuracy and reliability of risk data.
👍2
#CAPM Question #1068
After a budget change is approved, you will need to do all of the following except:
Anonymous Quiz
13%
a. Revise cost estimates.
11%
b. Update the project budget.
26%
c. Develop a new estimate at completion.
50%
d. Re-baseline the WBS.
🤔1
#PMP Question #3300
A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer features or low quality.
What should the project leader have done to ensure success?
Answers:
a. Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery.
b. Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints.
c. Asked the team to create an impediment log and keep it updated for use in the next sprint planning.
d. Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments.
👍2
#CPMAI Question #7217
How many AI winters have we previously had?
Anonymous Quiz
30%
a. 0
18%
b. 1
18%
c. 2
24%
d. 3
9%
e. 5
0%
f. 6
🤔5
#PfMP Question #2238
The portfolio positive or negative risk may impact all the following, except:
Anonymous Quiz
9%
a. Market leadership
14%
b. The organization
68%
c. Regulations in the market
9%
d. Benefits that the programs and projects generate
👍1
#PMP Question #5244
A new sales software development project is underway. The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.
Which project approach should the project manager take?
#PMP Question #455
A project manager is trying to settle a dispute between two team members. One says the systems should be integrated before testing, and the other maintains each system should be tested before integration. The project involves over 30 people, and 12 systems need to be integrated. The sponsor is demanding that integration happens on time.
What is the BEST statement the project manager can make to resolve the conflict?