#PMP Question #1647
A project team is planning the project scope for a new software development initiative. They have identified the major deliverables and are now working on breaking down the project into smaller, manageable components. The project manager needs to ensure that the scope is clearly defined and documented to avoid any misunderstandings later.
What does the scope baseline include?
#PMP Question #5373
An agile project is starting its seventh out of eight iterations. In a planning meeting, the team realized that an unidentified risk became an issue and the contingency reserve had to be used.
What should the project manager do?
๐Ÿ‘1
#PfMP Question #1873
Assume you are the portfolio manager for a public sector organization, and it has been part of a public-private partnership for three years for highway projects. You are making recommendations as to the next program to undertake. The head of your Highway Department in your State is questioning whether the partnership is the best approach or whether it is best to work on its own. You asked the Marketing manager for assistance, and she prepared a value-for-money analysis. This approach is useful in that it:
๐Ÿค”1
#PMP Question #3880
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing. The software update will be accomplished using an agile approach in order to minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches.
What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?
๐Ÿ”ฅ1
#PMP Question #4996
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting.
What should the project manager do?
Answers:
a. Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome.
b. Update the communications management plan and implement the change.
c. Meet with the project sponsor to discuss how to address the situation.
d. Meet with the stakeholder prior to the meeting to obtain their opinion.