Answers #5000
Anonymous Quiz
3%
a
56%
b
34%
c
6%
d
👍1
#PMP Question #4792
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
#PMP Question #5048
A compliance strategy was created during the planning phase of a project. During execution, the project manager left the organization and another project manager was assigned to the team.
What should the project manager do first to ensure the project is compliant?
#PMP Question #1046
The PMBOK covers information that is unique to project management. However, project managers must also utilize general management knowledge and application-specific knowledge in order to be successful. Application area knowledge has to do with specific practices surrounding industries, technology, or functions.
Which is an example of application area-specific knowledge?
#CAPM Question #2891
A software project using an agile approach is facing quality issues with every release, generating many production problems.
What should the project manager do to fix the problem and improve the quality?
Answers:
a. Facilitate a team workshop to identify root causes and pilot improvements to quality practices.
b. Increase peer reviews and require more approvals before merging code to raise accountability.
c. Ask the product owner to shift backlog priorities toward resolving defects and reducing technical debt.
d. Bring in external experts for a quality review and follow their recommended process changes.
👍1