#PMP Question #4647
A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on the regulation's requirements. Therefore, changes in product definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?
#PMP Question #5313
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain.
What should the project manager do now?
#PMP Question #5291
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.
How should the project manager address this situation?
Answers:
a. Ask the team to include the compliance requirement in the current sprint and deliver it.
b. Add the new compliance requirement to the backlog as the technical team does not have any capacity.
c. Include the compliance lead in the stakeholders list and wait for the next status meeting.
d. Collaborate with the compliance team member to review and prioritize the requirement's delivery.