Answers #5207
Anonymous Quiz
7%
a
7%
b
52%
c
33%
d
🤔1
#PMP Question #132
A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
#CAPM Question #4326
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
#PMP Question #4177
A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing. Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.
What should the project manager have done to avoid this situation?
Answers:
a. Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred.
b. Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays.
c. Met with the team, allowed team members to make decisions about what to do and established performance goals.
d. Conducted routine meetings and identified team members who are under performing.
Answers #4177
Anonymous Quiz
35%
a
5%
b
50%
c
10%
d
👍1
#PMP Question #3336
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.
What should the project manager do to realize benefits?
#PMP Question #3260
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production. One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
Answers:
a. Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.
b. Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.
c. Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.
d. Foster stakeholder participation by engaging them early on the backlog discussions.
Answers #3260
Anonymous Quiz
11%
a
22%
b
44%
c
22%
d
👍1