#PMP Question #1359
You are the project manager of a new home construction project that will create 112 new homes with an average of 17 double hung windows in each home. A finish carpenter has complained that a recent shipment of prefabricated windows lack the brass sash pulls and locks that had been installed in all previous shipments. You contact the supplier who agrees to provide the hardware for the current and future shipments.
You determine:
Answers:
a. That further action is unnecessary at this time.
b. That the scope of the project has changed since additional time will be required to install the hardware.
c. That the supplier is in breach of contract.
d. That a change order requiring that window hardware be pre-installed should be sent to the window supplier.
Answers #1359
Anonymous Quiz
9%
a
46%
b
11%
c
34%
d
👍1🔥1
#PMP Question #4713
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown above.
What should the team do next?
Answers:
a. Ask the product owner if some low-priority stories could be cut from the sprint.
b. Continue with the sprint as the progress shows buffers for potential interruptions.
c. Ask the project team to select any additional stories as they have additional capacity than planned.
d. Continue with the sprint work as planned and keep monitoring.
Answers #4713
Anonymous Quiz
17%
a
21%
b
17%
c
45%
d
👍1
#PMP Question #2734
During a project's initiation phase, a lessons-learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
Answers:
a. Discuss this issue with the project sponsor to request additional funding to implement mitigation.
b. Hire a construction management consultant to develop a comprehensive site execution plan.
c. Prequalify contractors with proven track records to eliminate productivity concerns.
d. Add construction productivity to the risk register and develop a mitigation strategy for site execution.
Answers #2734
Anonymous Quiz
8%
a
0%
b
8%
c
85%
d
1👍1
#PMP Question #5310
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months.
What should the project lead do next?
Answers:
a. Schedule meetings with the customer to determine their ability to support multiple incremental deliveries.
b. Work with the agile team to schedule the incremental deliveries to enable delivery of business value sooner to the customer.
c. Work with the stakeholder to understand what the concerns are while at the same time conveying the benefits of incremental deliveries.
d. Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.
1👍1
Answers #5310
Anonymous Quiz
6%
a
18%
b
61%
c
15%
d
2
#PMP Question #4496
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of timelines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
#PMP Question #1031
A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delays. The project manager does not agree with the costs submitted by the contractor for the missing materials.
What should the project manager do next?