#PMP Question #138
A project manager is overseeing a council project aimed at ensuring compliance with health, ecological, and environmental standards while strictly adhering to the council's values, policies, and procedures.
How should the project manager ensure the project's success?
Answers:
a. Enforce the project manager's authority over the contracting partner delivering to the council.
b. Engage a third-party consulting firm to oversee the project's implementation.
c. Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.
d. Regularly engage with stakeholders to align on project objectives, establish common goals, and agree on a shared plan.
Answers #138
Anonymous Quiz
8%
a
12%
b
4%
c
76%
d
🔥1
#PMP Question #3281
An organization in a regulated industry has decided to switch from a predictive to an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum, and the project manager is still accountable for the project outcomes. During the fourth sprint demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
Answers:
a. Have the team consult with the compliance officer to update the definition of done.
b. Have the product owner consult with the change control board (CCB) to have the necessary compliance requirements implemented.
c. Have the scrum master organize a weekly meeting with the compliance officer, the product owner, and the project team.
d. Have the product owner review the user stories in the product backlog with the compliance officer on a regular basis to identify any gaps.
Answers #3281
Anonymous Quiz
22%
a
25%
b
16%
c
38%
d
1🤔1
#PSM Question #4019
At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations. What factors may have led to this?
Answers:
a. The Scrum Team has not used the past Sprint Retrospectives effectively to inspect and adapt.
b. The Development Team has not been paying enough attention to technical quality.
c. The Development Team and the Product Owner are not having conversations around technical debt.
d. The Scrum Master has not ensured that the Scrum Team is transparent.
e. All of the factors in options A, B, C, D.
f. None of the factors in options A, B, C, D.
#CAPM Question #480
A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint.
If another problem with quality were to occur, what would be the BEST thing for the project manager to do?
#CAPM Question #960
Of the following, which conflict resolution strategy is likely to yield the most productive results?
Anonymous Quiz
5%
a. Withdrawing.
0%
b. Forcing.
14%
c. Compromising.
81%
d. Collaborating.
PgMP Certification Preparation Group starts September 9
The PgMP certification validates your expertise in managing interconnected projects to achieve strategic goals, showcasing your ability to coordinate complex initiatives and drive organizational success.

📘 Course Details
- Cost: €1000*
- Duration: 3 months (12 lessons)
- Full Access to KnowledgeMap platform
- Mentor: @TarasFedoruk

🗓 Open Session
Join the free onboarding on September 9 at 18:00 (Kyiv time) - https://calendar.app.google/sT4LjXdGZvda4CC67
🙋‍♂️ Got questions? Reach out to @AnatoliiSavin, Founder & Chief Mentor of KnowledgeMap, for expert guidance and support.

*Ways to Save
- Free training for Ukrainian veterans & military
- Flexible payments (2–3 installments)
- Early bird: 20% off if paid in full by September 9
- PMI Ukraine Chapter members: extra 10% discount
- Self-study option: KnowledgeMap subscription $9.99/month

Upcoming Groups
Next PgMP group: April 21, 2026
PMP: September 23, 2025
PMI-CP: October 7, 2025
📅 Full certification calendar: KnowledgeMap.pm/Marathon
🔥1
#CAPM Question #4814
After a project team has been working on a project for several months, the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
Answers:
a. Comply with the project sponsor's request to not archive the project artifacts.
b. Document the project sponsor's instructions as the archived project artifacts.
c. Archive the project artifacts on the project manager's local computer for future reference.
d. Consult with the project management office (PMO) for guidance on project artifacts.
#PMP Question #2961
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?
Answers:
a. Request that the project team change their task deliverables to reflect the project sponsor's requirements.
b. Set up a daily standup and request that the project sponsor attend to understand the project's tasks and deliverables.
c. Ask the project team to compile a project scope document and obtain approval from the project sponsor.
d. Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.