𝗞𝗻𝗼𝘄𝗹𝗲𝗱𝗴𝗲𝗠𝗮𝗽
1.97K subscribers
79 photos
219 links
https://KnowledgeMap.pm is your guide to professional certification (CAPM, PMP, PgMP, PfMP, PMI-ACP, PMI-PBA, PMI-RMP, PSM I-II)
Download Telegram
#PMP Question #138
A project manager is overseeing a council project aimed at ensuring compliance with health, ecological, and environmental standards while strictly adhering to the council's values, policies, and procedures.
How should the project manager ensure the project's success?
Answers:
a. Enforce the project manager's authority over the contracting partner delivering to the council.
b. Engage a third-party consulting firm to oversee the project's implementation.
c. Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.
d. Regularly engage with stakeholders to align on project objectives, establish common goals, and agree on a shared plan.
Answers #138
Anonymous Quiz
9%
a
13%
b
4%
c
74%
d
🔥1
#PMP Question #3281
An organization in a regulated industry has decided to switch from a predictive to an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum, and the project manager is still accountable for the project outcomes. During the fourth sprint demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
Answers:
a. Have the team consult with the compliance officer to update the definition of done.
b. Have the product owner consult with the change control board (CCB) to have the necessary compliance requirements implemented.
c. Have the scrum master organize a weekly meeting with the compliance officer, the product owner, and the project team.
d. Have the product owner review the user stories in the product backlog with the compliance officer on a regular basis to identify any gaps.
Answers #3281
Anonymous Quiz
23%
a
27%
b
13%
c
37%
d
1🤔1
#PSM Question #4019
At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations. What factors may have led to this?
Answers:
a. The Scrum Team has not used the past Sprint Retrospectives effectively to inspect and adapt.
b. The Development Team has not been paying enough attention to technical quality.
c. The Development Team and the Product Owner are not having conversations around technical debt.
d. The Scrum Master has not ensured that the Scrum Team is transparent.
e. All of the factors in options A, B, C, D.
f. None of the factors in options A, B, C, D.
#CAPM Question #480
A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint.
If another problem with quality were to occur, what would be the BEST thing for the project manager to do?
#CAPM Question #960
Of the following, which conflict resolution strategy is likely to yield the most productive results?
Anonymous Quiz
6%
a. Withdrawing.
0%
b. Forcing.
14%
c. Compromising.
81%
d. Collaborating.
PgMP Certification Preparation Group starts September 9
The PgMP certification validates your expertise in managing interconnected projects to achieve strategic goals, showcasing your ability to coordinate complex initiatives and drive organizational success.

📘 Course Details
- Cost: €1000*
- Duration: 3 months (12 lessons)
- Full Access to KnowledgeMap platform
- Mentor: @TarasFedoruk

🗓 Open Session
Join the free onboarding on September 9 at 18:00 (Kyiv time) - https://calendar.app.google/sT4LjXdGZvda4CC67
🙋‍♂️ Got questions? Reach out to @AnatoliiSavin, Founder & Chief Mentor of KnowledgeMap, for expert guidance and support.

*Ways to Save
- Free training for Ukrainian veterans & military
- Flexible payments (2–3 installments)
- Early bird: 20% off if paid in full by September 9
- PMI Ukraine Chapter members: extra 10% discount
- Self-study option: KnowledgeMap subscription $9.99/month

Upcoming Groups
Next PgMP group: April 21, 2026
PMP: September 23, 2025
PMI-CP: October 7, 2025
📅 Full certification calendar: KnowledgeMap.pm/Marathon
🔥1