#PMP Question #4828
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
#PMP Question #1157
A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.
How should these conflicts be resolved?
#PMP Question #138
A project manager is overseeing a council project aimed at ensuring compliance with health, ecological, and environmental standards while strictly adhering to the council's values, policies, and procedures.
How should the project manager ensure the project's success?
Answers:
a. Enforce the project manager's authority over the contracting partner delivering to the council.
b. Engage a third-party consulting firm to oversee the project's implementation.
c. Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.
d. Regularly engage with stakeholders to align on project objectives, establish common goals, and agree on a shared plan.
Answers #138
Anonymous Quiz
10%
a
10%
b
3%
c
77%
d
🔥1
#PMP Question #3281
An organization in a regulated industry has decided to switch from a predictive to an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum, and the project manager is still accountable for the project outcomes. During the fourth sprint demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
Answers:
a. Have the team consult with the compliance officer to update the definition of done.
b. Have the product owner consult with the change control board (CCB) to have the necessary compliance requirements implemented.
c. Have the scrum master organize a weekly meeting with the compliance officer, the product owner, and the project team.
d. Have the product owner review the user stories in the product backlog with the compliance officer on a regular basis to identify any gaps.
Answers #3281
Anonymous Quiz
23%
a
21%
b
18%
c
38%
d
1🤔1
#PSM Question #4019
At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations. What factors may have led to this?
Answers:
a. The Scrum Team has not used the past Sprint Retrospectives effectively to inspect and adapt.
b. The Development Team has not been paying enough attention to technical quality.
c. The Development Team and the Product Owner are not having conversations around technical debt.
d. The Scrum Master has not ensured that the Scrum Team is transparent.
e. All of the factors in options A, B, C, D.
f. None of the factors in options A, B, C, D.
#CAPM Question #480
A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint.
If another problem with quality were to occur, what would be the BEST thing for the project manager to do?
#CAPM Question #960
Of the following, which conflict resolution strategy is likely to yield the most productive results?
Anonymous Quiz
6%
a. Withdrawing.
0%
b. Forcing.
15%
c. Compromising.
79%
d. Collaborating.