#PMP Question #5239
A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
Answers:
a. Increase resources on the technical design to enable a decision to proceed as this is a quick return project.
b. Increase the time spent on project development to improve the level of confidence to validate the financial evaluation.
c. Conduct a stakeholder survey with the plant operators to establish the probability of this project reducing the cost of utilities.
d. Stop any further project development and commence with the implementation as there is no need to seek further approval.
A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
Answers:
a. Increase resources on the technical design to enable a decision to proceed as this is a quick return project.
b. Increase the time spent on project development to improve the level of confidence to validate the financial evaluation.
c. Conduct a stakeholder survey with the plant operators to establish the probability of this project reducing the cost of utilities.
d. Stop any further project development and commence with the implementation as there is no need to seek further approval.
What strategies and techniques does the PMBOK® Guide (7th Edition) recommend to prevent communication issues and ensure stakeholder engagement throughout a project?
Referer to:https://knowledgemap.pm/certifications/pmi-cp/prepare-for-the-certification-exam/2-2-prevent-communication-issues-from-occuring-and-ensure-stakeholders-are-engaged/
#StakeholderEngagement #PMICP #PMI #Certification
Referer to:https://knowledgemap.pm/certifications/pmi-cp/prepare-for-the-certification-exam/2-2-prevent-communication-issues-from-occuring-and-ensure-stakeholders-are-engaged/
#StakeholderEngagement #PMICP #PMI #Certification
KnowledgeMap
PMI-CP Prevent Communication Issues
PMI-CP prevent communication issues by engaging stakeholders early and using effective communication management strategies.
👍2
#CAPM Question #1882
The term "last responsible moment" refers to the moment at which:
The term "last responsible moment" refers to the moment at which:
Anonymous Quiz
27%
a. the iteration testing deadline arrives and code testing must stop.
27%
b. failing to make a decision eliminates an important alternative.
11%
c. release planning is complete and the first iteration planning starts.
35%
d. the implementation date is set and sponsor approval has been received.
🤔1
What are the key enablers of the "Empower Team Members and Stakeholders" task, and which resources should be reviewed to learn about it in preparation for the PMP Certification?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-4-empower-team-members-and-stakeholders/
#PMP #Certification #TeamEmpowerment #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-4-empower-team-members-and-stakeholders/
#PMP #Certification #TeamEmpowerment #ProjectManagement
KnowledgeMap
PMP Empower Team Members and Stakeholders
Empower team members and stakeholders for PMP certification with key enablers and essential resources from PMBOK and Agile Practice Guide.
👍1
#PMP Question #5099
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
Answers:
a. Ask to execute the project with a predictive approach since there is a budget and schedule risk.
b. Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.
c. Plan for training on agile tools and techniques used in the defined hybrid methodology for consistent application by all team members.
d. Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
Answers:
a. Ask to execute the project with a predictive approach since there is a budget and schedule risk.
b. Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.
c. Plan for training on agile tools and techniques used in the defined hybrid methodology for consistent application by all team members.
d. Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.
What steps must be followed to submit payment after receiving approval for the PgMP certification application?
Referer to:https://knowledgemap.pm/certifications/pgmp/pgmp-certification-process/submit-payment/
#PgMP #Certification #PMI #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pgmp/pgmp-certification-process/submit-payment/
#PgMP #Certification #PMI #ProjectManagement
KnowledgeMap
PgMP Certification Payment Process
Learn how to complete the Submit PgMP Certification Payment Process step by step after your application is approved by PMI.
👍2
#PMP Question #4765
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project.
What should the project manager do to alleviate the stakeholders' concerns?
Answers:
a. Send communications for clarification so there is a full understanding of the situation.
b. Demonstrate the performance indexes and recommend corrective actions to the stakeholders.
c. Schedule a kick-off session to explain the problems of the project and gain approval and support.
d. Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders.
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project.
What should the project manager do to alleviate the stakeholders' concerns?
Answers:
a. Send communications for clarification so there is a full understanding of the situation.
b. Demonstrate the performance indexes and recommend corrective actions to the stakeholders.
c. Schedule a kick-off session to explain the problems of the project and gain approval and support.
d. Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders.
What is the purpose of the PgMP certification, and how does it benefit senior program managers?
Referer to:https://knowledgemap.pm/certifications/pgmp/
#PgMP #Certification #ProgramManagement #StrategicLeadership
Referer to:https://knowledgemap.pm/certifications/pgmp/
#PgMP #Certification #ProgramManagement #StrategicLeadership
KnowledgeMap
PgMP Certification
Earn PgMP certification to demonstrate your expertise in program management and lead projects that align with strategic goals.
🔥1
#CAPM Question #3784
When controlling a schedule what data analysis technique would NOT be used?
When controlling a schedule what data analysis technique would NOT be used?
Anonymous Quiz
33%
a. Performance reviews.
21%
b. Iteration burndown charts.
16%
c. Earned value analysis.
30%
d. Schedule change control
👏1
How do you schedule your PMI-CP™ certification exam once you become eligible?
Referer to:https://knowledgemap.pm/certifications/pmi-cp/pmi-cp-certification-process/schedule-exam-appointment/
#PMICP #ProjectManagement #PMI
Referer to:https://knowledgemap.pm/certifications/pmi-cp/pmi-cp-certification-process/schedule-exam-appointment/
#PMICP #ProjectManagement #PMI
KnowledgeMap
PMI-CP Exam Scheduling
Learn about PMI-CP certification exam scheduling, including how to use your eligibility code to book your test online or by phone.
👍1
#PMP Question #2734
During a project's initiation phase, a lessons-learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
Answers:
a. Discuss this issue with the project sponsor to request additional funding to implement mitigation.
b. Hire a construction management consultant to develop a comprehensive site execution plan.
c. Prequalify contractors with proven track records to eliminate productivity concerns.
d. Add construction productivity to the risk register and develop a mitigation strategy for site execution.
During a project's initiation phase, a lessons-learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
Answers:
a. Discuss this issue with the project sponsor to request additional funding to implement mitigation.
b. Hire a construction management consultant to develop a comprehensive site execution plan.
c. Prequalify contractors with proven track records to eliminate productivity concerns.
d. Add construction productivity to the risk register and develop a mitigation strategy for site execution.
What are the key practices and leadership behaviors that enable agile teams to overcome silos and foster collaboration for better value delivery?
Referer to:https://knowledgemap.pm/certifications/acp/domain-1-mindset/acp-promote-collaborative-team-environment/
#Agile #PMIACP #Collaboration
Referer to:https://knowledgemap.pm/certifications/acp/domain-1-mindset/acp-promote-collaborative-team-environment/
#Agile #PMIACP #Collaboration
KnowledgeMap
PMI-ACP Collaboration
Discover how PMI-ACP collaboration and communication drive success in agile project delivery and team dynamics.
👍2
#PMP Question #5366
A new project manager is managing a hybrid project. The project manager wants to be a servant leader to support the team by removing impediments but is not receiving feedback from the team about the issues and risks they are facing.
What should the project manager do?
A new project manager is managing a hybrid project. The project manager wants to be a servant leader to support the team by removing impediments but is not receiving feedback from the team about the issues and risks they are facing.
What should the project manager do?
👍1
What are the key steps and techniques an agile leader should use to identify and resolve conflicts constructively within an agile team?
Referer to:https://knowledgemap.pm/certifications/acp/domain-2-leadership/acp-facilitate-conflict-management/
#Agile #Leadership #PMIACP #TeamCollaboration
Referer to:https://knowledgemap.pm/certifications/acp/domain-2-leadership/acp-facilitate-conflict-management/
#Agile #Leadership #PMIACP #TeamCollaboration
KnowledgeMap
PMI-ACP Facilitate Conflict Management
PMI-ACP Facilitate Conflict Management helps agile leaders resolve conflicts and improve team collaboration.
👍1
#PMP Question #4774
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional managers have expressed concerns about the use of new tools on such an important project.
What should the project manager do?
Answers:
a. Review the adaptive tools' impact and obtain agreement from the functional managers.
b. Follow the functional managers' recommendation to implement only predictive tools in the project.
c. Make the decision on which project approach to use that would best fit the project.
d. Follow the project management office's (PMOs) request to implement the adaptive tools in the project.
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional managers have expressed concerns about the use of new tools on such an important project.
What should the project manager do?
Answers:
a. Review the adaptive tools' impact and obtain agreement from the functional managers.
b. Follow the functional managers' recommendation to implement only predictive tools in the project.
c. Make the decision on which project approach to use that would best fit the project.
d. Follow the project management office's (PMOs) request to implement the adaptive tools in the project.