#PMP Question #5239
A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years.
What should the project manager do to expedite the project delivery?
Answers:
a. Increase resources on the technical design to enable a decision to proceed as this is a quick return project.
b. Increase the time spent on project development to improve the level of confidence to validate the financial evaluation.
c. Conduct a stakeholder survey with the plant operators to establish the probability of this project reducing the cost of utilities.
d. Stop any further project development and commence with the implementation as there is no need to seek further approval.
Answers #5239
Anonymous Quiz
34%
a
11%
b
51%
c
4%
d
🔥1
#PMP Question #5099
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
Answers:
a. Ask to execute the project with a predictive approach since there is a budget and schedule risk.
b. Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.
c. Plan for training on agile tools and techniques used in the defined hybrid methodology for consistent application by all team members.
d. Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.
#PMP Question #4765
A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project.
What should the project manager do to alleviate the stakeholders' concerns?
Answers:
a. Send communications for clarification so there is a full understanding of the situation.
b. Demonstrate the performance indexes and recommend corrective actions to the stakeholders.
c. Schedule a kick-off session to explain the problems of the project and gain approval and support.
d. Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders.
#CAPM Question #3784
When controlling a schedule what data analysis technique would NOT be used?
Anonymous Quiz
33%
a. Performance reviews.
21%
b. Iteration burndown charts.
16%
c. Earned value analysis.
30%
d. Schedule change control
👏1
#PMP Question #2734
During a project's initiation phase, a lessons-learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
Answers:
a. Discuss this issue with the project sponsor to request additional funding to implement mitigation.
b. Hire a construction management consultant to develop a comprehensive site execution plan.
c. Prequalify contractors with proven track records to eliminate productivity concerns.
d. Add construction productivity to the risk register and develop a mitigation strategy for site execution.
#PMP Question #5366
A new project manager is managing a hybrid project. The project manager wants to be a servant leader to support the team by removing impediments but is not receiving feedback from the team about the issues and risks they are facing.
What should the project manager do?
#PMP Question #4774
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional managers have expressed concerns about the use of new tools on such an important project.
What should the project manager do?
Answers:
a. Review the adaptive tools' impact and obtain agreement from the functional managers.
b. Follow the functional managers' recommendation to implement only predictive tools in the project.
c. Make the decision on which project approach to use that would best fit the project.
d. Follow the project management office's (PMOs) request to implement the adaptive tools in the project.
Answers #4774
Anonymous Quiz
63%
a
0%
b
20%
c
17%
d