#PMP Question #2897
The Scrum team working with the quality department has been drifting away from the business unit due to unclear product requirements. Now, in the third sprint, both teams have been at a standstill for several days.
What should the project leader do to resolve this situation?
#PfMP Question #2177
A portfolio manager is looking for a starting point to develop the Portfolio.
Which of the following is right?
Anonymous Quiz
46%
a. Portfolio Charter
21%
b. Inventory of work
4%
c. Portfolio Communication Plan
29%
d. Portfolio Roadmap
#CAPM Question #1803
Who is responsible for making sure that each user story is associated with at least one user role or persona?
Anonymous Quiz
6%
a. User
69%
b. Developer
18%
c. Customer
8%
d. Persona
#PMP Question #5131
A project manager and project team have brought a project back on track after mapping and removing impediments. During the current sprint, the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously. However, the tasks do not have the same result as the impediment.
What should the project manager do?
#PMP Question #3319
A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the beginning of the project have changed.
What should the project manager do?
#PMP Question #712
During project executing, the project manager determines that a change is needed to material purchased for the project. The project manager calls a meeting of the team to plan how to make the change.
This is an example of: