#PMP Question #5343
A project team has been together for a long time and has been led by three different project managers. Lately, the performance of one of the team members has been declining and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and sustained?
๐—ž๐—ป๐—ผ๐˜„๐—น๐—ฒ๐—ฑ๐—ด๐—ฒ๐— ๐—ฎ๐—ฝ
๐Ÿ†•๐Ÿ””Join Our April Group of ๐Ÿ” ๐Ÿ” ๐Ÿ” -๐Ÿ” ๐Ÿ” ๐Ÿ”  Prep! Training Starts Soon โ€“ You Still Have Time to Enroll! If you analyze requirements or drive business change, the PMI-PBA certification is for you. โ„น๏ธAbout the Preparation Course: โž– Price: โ‚ฌ555โญ๏ธ โž– Duration: 3 monthsโ€ฆ
Still deciding whether to join the PMI-PBA Prep Group? Here's a great reason to say yes!

Your mentor for this training will be Denis Gobov ( @Dgobov ):
- Business analyst and trainer with more than 20  years of experience.
- Head of Business Analysis Capability at DataArt
- Editor at artofba.com/blog
- The co-author of the certification exam for CBAP based on BABOK 3.0.
- The first Ukrainian analyst who passed certification exams from leading organizations in business analysis and requirement engineering areas: CBAP (IIBA), PMI-PBA (PMI), CPRE (IREB).
- PhD
- Winner of the award "Best professional in the field of business analysis in 2013 and 2016โ€, IT Ukraine Association and "The Best Business Analyst in 2017", ITNetwork

โœ… Register for the free onboarding session: calendar.app.google/KvpVeiefSr1MNjAJA
๐Ÿ’ฌ Join the group chat on Telegram: t.me/+4kd3mhEDQS5lOTI6

Letโ€™s get you PBA-ready! ๐Ÿ’ผ๐Ÿ“š
๐Ÿ”ฅ2
#PMI-RMP Question #1546
One of the risks identi๏ฌed during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.
What should the project manager do?
#PfMP Question #2245
A portfolio team member is confused about what is meant by organizational resources. Which of the following is possibly one of the organizational resources?
Anonymous Quiz
3%
a. Funds
16%
b. Tangible and intangible assets
15%
c. Program and project managers and subject matter experts
66%
d. All the options
๐Ÿ‘2
#PMP Question #4964
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected.
What should the project manager do?
Answers:
a. Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project.
b. Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes.
c. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
d. Explain that the distribution of important news can only be done using traceable communication methods.